Question 1 of 50
Recently you have been
assigned as a Product Owner to the Scrum team that you had never worked with
before. One week later one of your company's managers approaches you and asks
to confirm that the project will be finished by the 6th of March. He says that
he reviewed estimates given by your team and needs a commitment guarantee it
will be finished to the exact date. What is the most likely problem in this
situation?
Correct answer: B)
You chose: B)
You chose: B)
A)
The
Manager should approach a Scrum Master not you
B)
Many
managers confuse estimates with commitments. As soon as a team expresses an
estimate they are forced to commit to it
C)
You
have been assigned to the project recently therefore you are not able to make
any commitments yet
D)
Agile
teams don't make any commitments to specific dates
Points: 1 out of 1
Feedback:
An estimate is a probability and a commitment cannot be made to a probability. Commitments are made to dates. Normally the date that a team is asked (or told) to commit to is one to which they would assign a less than 100% probability.
An estimate is a probability and a commitment cannot be made to a probability. Commitments are made to dates. Normally the date that a team is asked (or told) to commit to is one to which they would assign a less than 100% probability.
Question 2 of 50
At the start of release
planning, the team and product owner collaboratively explored the product
owner's conditions of satisfaction. Common factors in her conditions of
satisfaction included scope, schedule, and budget. Why quality was not included
in this list?
Correct answer: D)
You chose: D)
You chose: D)
A)
Quality
is not considered as one of the common factors in product owner's conditions of
satisfaction
B)
Quality
is usually negotiated during iteration planning
C)
Quality
is usually negotiated between Scrum Master and Product Owner, not the Team
D)
Agile
teams typically prefer to treat quality as non-negotiable
Points: 1 out of 1
Feedback:
Agile treats quality as non-negotiable. On the contrary, standard project management considers quality as negotiable factor and Project Manager is allowed to drop the quality when needed.
Agile treats quality as non-negotiable. On the contrary, standard project management considers quality as negotiable factor and Project Manager is allowed to drop the quality when needed.
Question 3 of 50
It is possible that the
newly discovered tasks will take long enough that they cannot be completed
during the iteration. They may need to reduce the functionality of a story or
drop one entirely. With whom should the team discuss the possible solutions in
this situation?
Correct answer: A)
You chose: A)
You chose: A)
A)
Product
Owner
B)
Scrum
Master
C)
Upper
Management
D)
Stakeholders
Points: 1 out of 1
Feedback:
It is possible that the newly discovered tasks will take long enough that they cannot be completed during the iteration. In that case, the team will need to discuss the situation with the Product Owner and see if there is still a way to meet the iteration goal; they may need
to reduce the functionality of a story or drop one entirely.
It is possible that the newly discovered tasks will take long enough that they cannot be completed during the iteration. In that case, the team will need to discuss the situation with the Product Owner and see if there is still a way to meet the iteration goal; they may need
to reduce the functionality of a story or drop one entirely.
Question 4 of 50
What is the best length of
an iteration in Scrum?
Correct answer: B)
You chose: B)
You chose: B)
A)
1
week
B)
There
is no ideal iteration length. It depends on the project and can vary
C)
2
weeks
D)
1
month
Points: 1 out of 1
Feedback:
There's no one magic iteration duration that is right for all teams under all circumstances. The right length for a team on one project may not be the right length for that same team on a different project.
There's no one magic iteration duration that is right for all teams under all circumstances. The right length for a team on one project may not be the right length for that same team on a different project.
Question 5 of 50
Is it acceptable to extend
the iteration for a few days in order to finish everything in the plan?
Correct answer: B)
You chose: B)
You chose: B)
A)
It
Depends
B)
It
is not acceptable. Iteration is timeboxed
C)
Yes,
you can extend an iteration in rare situations
D)
Acceptable
if the Scrum Master took a decision
Points: 1 out of 1
Feedback:
In your enthusiasm to demonstrate progress, be careful not to step over the line. Borderline behavior includes glossing over known defects in an iteration demo, taking credit for stories that are not 100 percent complete, and extending the iteration for a few days in order to finish everything in the plan.
In your enthusiasm to demonstrate progress, be careful not to step over the line. Borderline behavior includes glossing over known defects in an iteration demo, taking credit for stories that are not 100 percent complete, and extending the iteration for a few days in order to finish everything in the plan.
Question 6 of 50
Who "owns"
iteration demo in Scrum?
Correct answer: C)
You chose: D)
You chose: D)
A)
Product
Manager
B)
The
Scrum Master
C)
The
Product Owner
D)
The
Team
Points: 0 out of 1
Feedback:
The Product Owner conducts an Iteration Demo meeting.
The Product Owner conducts an Iteration Demo meeting.
Question 7 of 50
You are a Scrum Master in
a Scrum team. The Product Owner doesn't want to prioritize items in the Product
Backlog. He says everything is important. What is the best you can do?
Correct answer: B)
You chose: D)
You chose: D)
A)
Let
the Team work without prioritizing. Anyway, you will have to deliver all the
features. It is not a critical problem
B)
Be
firm and insist on prioritizing
C)
Prioritize
the Product Backlog yourself
D)
Let
the Team decide which features are most important
Points: 0 out of 1
Feedback:
Be firm. Yes, everything is important, but something has to come first and something will come last. Someone has to make the tough schedule decisions. That's the Product Owner's job.
Be firm. Yes, everything is important, but something has to come first and something will come last. Someone has to make the tough schedule decisions. That's the Product Owner's job.
Question 8 of 50
What is the longest
iteration duration allowed in Scrum?
Correct answer: D)
You chose: D)
You chose: D)
A)
2
Weeks
B)
3
Weeks
C)
2
Months
D)
1
Month
Points: 1 out of 1
Feedback:
Iteration is a one cycle within a project. In Scrum, this cycle is maximum 30 sequential calendar days, or a Sprint.
Iteration is a one cycle within a project. In Scrum, this cycle is maximum 30 sequential calendar days, or a Sprint.
Question 9 of 50
Who are referred to as
"Pigs" in Scrum?
Correct answer: A)
You chose: A)
You chose: A)
A)
The
Product Owner, the Scrum Master and The Team
B)
The
Stakeholders
C)
The
Upper Management
D)
The
Customer
Points: 1 out of 1
Feedback:
Someone occupying one of the three Scrum roles (Team, Product Owner, Scrum Master) who has made a commitment and has the authority to fulfill it.
Someone occupying one of the three Scrum roles (Team, Product Owner, Scrum Master) who has made a commitment and has the authority to fulfill it.
Question 10 of 50
Who are referred to as
"Chicken" in Scrum?
Correct answer: B)
You chose: B)
You chose: B)
A)
The
Product Owner, The Scrum Master and The Team
B)
Anyone
except one of the three roles in Scrum (The Team, The Product Owner, The Scrum
Master)
C)
The
Customer
D)
The
Team
Points: 1 out of 1
Feedback:
Someone occupying one of the three Scrum roles (The Team, The Product Owner, The Scrum Master) who has made a commitment and has the authority to fulfill it. Anyone else is called a "Chicken".
Someone occupying one of the three Scrum roles (The Team, The Product Owner, The Scrum Master) who has made a commitment and has the authority to fulfill it. Anyone else is called a "Chicken".
Question 11 of 50
What of the following
characterizes the Scrum incorrectly?
Correct answer: C)
You chose: C)
You chose: C)
A)
Scrum
is a framework
B)
Scrum
is used for
complex work in which it is impossible to predict everything that will occur
complex work in which it is impossible to predict everything that will occur
C)
Scrum
uses a predictive approach
D)
Scrum
is a very simple process for managing complex projects
Points: 1 out of 1
Feedback:
Scrum uses a fact-based decision making, a lot better than front-end-loaded predictive approaches.
Scrum uses a fact-based decision making, a lot better than front-end-loaded predictive approaches.
Question 12 of 50
How many roles included in
Scrum?
Correct answer: A)
You chose: A)
You chose: A)
A)
3
B)
2
C)
4
D)
1
Points: 1 out of 1
Feedback:
There are only three Scrum roles: the Product Owner, the Team, and the Scrum Master.
There are only three Scrum roles: the Product Owner, the Team, and the Scrum Master.
Question 13 of 50
All management
responsibilities in a project are divided among which roles in Scrum?
Correct answer: B)
You chose: B)
You chose: B)
A)
The
Scrum Master and the Product Owner
B)
The
Team, the Scrum Master, the Product Owner
C)
The
Team, the Product Owner
D)
The
Team, the Scrum Master
Points: 1 out of 1
Feedback:
There are only three Scrum roles: the Product Owner, the Team, and the Scrum Master. All management responsibilities in a project are divided among these three roles.
There are only three Scrum roles: the Product Owner, the Team, and the Scrum Master. All management responsibilities in a project are divided among these three roles.
Question 14 of 50
Who is responsible for
representing the interests of everyone with a stake in the project and its
resulting system in Scrum?
Correct answer: C)
You chose: C)
You chose: C)
A)
The
Team
B)
The
Scrum Master
C)
The
Product Owner
D)
The
Scrum Master and the Product Owner
Points: 1 out of 1
Feedback:
The Product Owner is responsible for representing the interests of everyone with a stake in the project and its resulting system.
The Product Owner is responsible for representing the interests of everyone with a stake in the project and its resulting system.
Question 15 of 50
Who provides ongoing
funding of the project in Scrum?
Correct answer: D)
You chose: B)
You chose: B)
A)
The
Project Manager
B)
The
Management
C)
The
Scrum Master
D)
The
Product Owner
Points: 0 out of 1
Feedback:
The Product Owner achieves initial and ongoing funding for the project by creating the project's initial overall requirements, return on investment (ROI) objectives, and release plans.
The Product Owner achieves initial and ongoing funding for the project by creating the project's initial overall requirements, return on investment (ROI) objectives, and release plans.
Question 16 of 50
One of the following
definitions describes the correct characteristics of the Scrum team:
Correct answer: A)
You chose: A)
You chose: A)
A)
Self-managing,
Self-organizing, and Cross-functional
B)
Self-directing,
Self-organizing, and Cross-functional
C)
Self-directing,
Self-empowered, and Cross-functional
D)
Self-monitoring,
Self-managing, and Self-functioning
Points: 1 out of 1
Feedback:
Teams are self-managing, self-organizing, and cross-functional, and they are responsible for figuring out how to turn Product Backlog into an increment of functionality within an iteration and managing their own work to do so.
Teams are self-managing, self-organizing, and cross-functional, and they are responsible for figuring out how to turn Product Backlog into an increment of functionality within an iteration and managing their own work to do so.
Question 17 of 50
A Scrum Master is often
compared to:
Correct answer: A)
You chose: C)
You chose: C)
A)
A
ship dog
B)
A
Pig
C)
A
chicken
D)
A
camel
Points: 0 out of 1
Feedback:
A Scrum Master is often compared to a sheepdog, responsible for keeping the flock together and the wolves away.
A Scrum Master is often compared to a sheepdog, responsible for keeping the flock together and the wolves away.
Question 18 of 50
Who is responsible for the
ROI of the project in Scrum?
Correct answer: B)
You chose: B)
You chose: B)
A)
The
Scrum Master
B)
The
Product Owner
C)
The
Team
D)
The
Project Manager
Points: 1 out of 1
Feedback:
The Product Owner is responsible for the ROI of the project, which usually means that the Product Owner chooses to develop product functionality that solves critical business problems.
The Product Owner is responsible for the ROI of the project, which usually means that the Product Owner chooses to develop product functionality that solves critical business problems.
Question 19 of 50
What technique does the
Scrum use to require that every slice of functionality created by the
developers be complete?
Correct answer: D)
You chose: A)
You chose: A)
A)
Sushi
B)
Deming
cycle
C)
Frequent
feedback loops
D)
Sashimi
Points: 0 out of 1
Feedback:
Similar to the way every other slice tastes. Scrum uses the sashimi technique to require that every slice of functionality created by the developers be complete.
Similar to the way every other slice tastes. Scrum uses the sashimi technique to require that every slice of functionality created by the developers be complete.
Question 20 of 50
Who has to manage the
Scrum Team?
Correct answer: A)
You chose: A)
You chose: A)
A)
The
Team
B)
The
Scrum Master
C)
The
Product Owner
D)
The
Management
Points: 1 out of 1
Feedback:
It is not the Scrum Master's job to manage the Team. The Team has to learn to manage itself, to constantly adjust its methods in order to optimize its chances of success.
It is not the Scrum Master's job to manage the Team. The Team has to learn to manage itself, to constantly adjust its methods in order to optimize its chances of success.
Question 21 of 50
Who is required to attend
the Retrospective Meeting?
Correct answer: B)
You chose: B)
You chose: B)
A)
The
Team, the Scrum Master, and the Product Owner
B)
The
Team and The Scrum Master
C)
The
Team
D)
The
Team and the Product Owner
Points: 1 out of 1
Feedback:
It is attended only by the Team, the Scrum Master, and the Product Owner. The Product Owner is optional.
It is attended only by the Team, the Scrum Master, and the Product Owner. The Product Owner is optional.
Question 22 of 50
What is the most popular
Agile methodology?
Correct answer: C)
You chose: C)
You chose: C)
A)
FDD
B)
Waterfall
C)
Scrum
D)
XP
Points: 1 out of 1
Feedback:
Scrum is the most popular of the Agile methods. It is frequently used in conjunction with Extreme Programming (XP).
Scrum is the most popular of the Agile methods. It is frequently used in conjunction with Extreme Programming (XP).
Question 23 of 50
What of the following is
not true of the Self-organization in Scrum?
Correct answer: D)
You chose: B)
You chose: B)
A)
Self-organization
is not an option in Scrum
B)
Self-organized
teams are highly disciplined
C)
High
trust and high commitment is an outcome of self-organizing teams
D)
Self-organization
implies a laissez-faire approach
Points: 0 out of 1
Feedback:
Self-organization is not an option in Scrum; it is a core principle. Without this, high performing teams will not happen. Self-organization does not at all imply a laissez-faire approach; on the contrary, self-organized teams are highly disciplined. They are encouraged to take reasonable risks and to learn through failure and self-reflection. High trust and high commitment is an automatic outcome of truly self-organizing teams.
Self-organization is not an option in Scrum; it is a core principle. Without this, high performing teams will not happen. Self-organization does not at all imply a laissez-faire approach; on the contrary, self-organized teams are highly disciplined. They are encouraged to take reasonable risks and to learn through failure and self-reflection. High trust and high commitment is an automatic outcome of truly self-organizing teams.
Question 24 of 50
Who gathers requirements
in Scrum?
Correct answer: A)
You chose: A)
You chose: A)
A)
The
Product Owner
B)
The
Scrum Master
C)
The
Team
D)
The
Product Manager
Points: 1 out of 1
Feedback:
The responsibilities of the Product Owner role are: Working on a shared vision, Gathering requirements, Managing and prioritizing the Product Backlog, Accepting the software at the end of each iteration, Managing the release plan, The profitability of the project (ROI).
The responsibilities of the Product Owner role are: Working on a shared vision, Gathering requirements, Managing and prioritizing the Product Backlog, Accepting the software at the end of each iteration, Managing the release plan, The profitability of the project (ROI).
Question 25 of 50
Whose responsibility is to
socialize Scrum to the greater organization?
Correct answer: B)
You chose: C)
You chose: C)
A)
The
Project Manager's
B)
The
Scrum Master's
C)
The
Product Owner's
D)
The
Manager's
Points: 0 out of 1
Feedback:
The responsibilities of the Scrum Master role are: Empowering and shepherding the team, Removing impediments, Keeping the process moving, Socializing Scrum to the greater organization.
The responsibilities of the Scrum Master role are: Empowering and shepherding the team, Removing impediments, Keeping the process moving, Socializing Scrum to the greater organization.
Question 26 of 50
What metaphor does not
expresses the role of the Scrum Master in Scrum?
Correct answer: C)
You chose: A)
You chose: A)
A)
Bulldozer
B)
Ship
dog
C)
Chicken
D)
Trainer
Points: 0 out of 1
Feedback:
Metaphor: The Scrum Master is a facilitator, coach, mentor and bulldozer! A Scrum Master is often compared to a sheepdog, responsible for keeping the flock together and the wolves away. Chicken refers to those outside the three Scrum roles.
Metaphor: The Scrum Master is a facilitator, coach, mentor and bulldozer! A Scrum Master is often compared to a sheepdog, responsible for keeping the flock together and the wolves away. Chicken refers to those outside the three Scrum roles.
Question 27 of 50
What is the leading
indicator of whether the Scrum Team will meet its commitment at the end of the
sprint?
Correct answer: B)
You chose: B)
You chose: B)
A)
The
Sprint Backlog
B)
The
Sprint Burndown
C)
The
Scrum Board
D)
The
Team's commitment
Points: 1 out of 1
Feedback:
The sprint burndown chart is designed to help the team monitor its progress and be a leading indicator of whether it will meet its commitment at the end of the sprint. The classic format requires teams to estimate the duration of each task in hours and on a daily basis to chart the total remaining hours for all uncompleted tasks.
The sprint burndown chart is designed to help the team monitor its progress and be a leading indicator of whether it will meet its commitment at the end of the sprint. The classic format requires teams to estimate the duration of each task in hours and on a daily basis to chart the total remaining hours for all uncompleted tasks.
Question 28 of 50
What is the best time to
introduce or take away team members in a Scrum team?
Correct answer: D)
You chose: D)
You chose: D)
A)
When
needed
B)
Between
releases
C)
Before
project starts
D)
Between
sprints
Points: 1 out of 1
Feedback:
It's important to keep the configuration of the team as stable as possible, and introduce or take away team members between sprints. Remember the rule: The people who made the commitment deliver the commitment.
It's important to keep the configuration of the team as stable as possible, and introduce or take away team members between sprints. Remember the rule: The people who made the commitment deliver the commitment.
Question 29 of 50
There is memory-jogger
describing right qualities of the successful Product Owner. It is:
Correct answer: B)
You chose: A)
You chose: A)
A)
DEEP
B)
CRACK
C)
INVEST
D)
CRUEL
Points: 0 out of 1
Feedback:
An effective product owner is Committed, Responsible, Authorized, Collaborative, and Knowledgeable(CRACK).
An effective product owner is Committed, Responsible, Authorized, Collaborative, and Knowledgeable(CRACK).
Question 30 of 50
You are a Scrum Master of
the Scrum Team. Back after the holidays, you find that your team is divided
into 2 groups, which fiercely arguing over whether to use the new framework or
not. None of the group wants to give up and defends their point of view. What
level of conflict are you observing as a Scrum Master?
Correct answer: B)
You chose: D)
You chose: D)
A)
Level
5
B)
Level
3
C)
Level
1
D)
Level
4
Points: 0 out of 1
Feedback:
At level 3, the aim is to win. A compounding effect occurs as prior conflicts and problems remain unresolved. Often, multiple issues cluster into larger issues or create a "cause." Factions emerge in this fertile ground from which misunderstandings and power politics arise.
At level 3, the aim is to win. A compounding effect occurs as prior conflicts and problems remain unresolved. Often, multiple issues cluster into larger issues or create a "cause." Factions emerge in this fertile ground from which misunderstandings and power politics arise.
Question 31 of 50
Who ensures that work is
aligned with leadership's direction and Product Vision?
Correct answer: A)
You chose: A)
You chose: A)
A)
The
Product Owner
B)
The
Scrum Master
C)
The
Team
D)
An
Agile Coach
Points: 1 out of 1
Feedback:
Product owner ensures work is aligned with leadership's direction and product vision.
Product owner ensures work is aligned with leadership's direction and product vision.
Question 32 of 50
What Scrum event can be
considered an analogue of traditional management "status meeting"?
Correct answer: A)
You chose: D)
You chose: D)
A)
Review
Meeting
B)
Stand-Up
meeting
C)
Retrospective
Meeting
D)
Planning
Meeting
Points: 0 out of 1
Question 33 of 50
The Team owns which kind
of Scrum plan?
Correct answer: C)
You chose: C)
You chose: C)
A)
Roadmap
Plan
B)
Release
Plan
C)
Iteration
Plan
D)
Product
Vision
Points: 1 out of 1
Feedback:
The Team owns iteration plan only. Roadmap and Release plans are owned by the Product Owner.
The Team owns iteration plan only. Roadmap and Release plans are owned by the Product Owner.
Question 34 of 50
Who is(are) the creator(s)
of Scrum?
Correct answer: C)
You chose: C)
You chose: C)
A)
Ken
Schwaber
B)
Jeff
Sutherland
C)
Ken
Schwaber and Jeff Sutherland
D)
Alistair
Cockburn
Points: 1 out of 1
Feedback:
Scrum was developed and sustained by Ken Schwaber and Jeff Sutherland.
Scrum was developed and sustained by Ken Schwaber and Jeff Sutherland.
Question 35 of 50
Tom presented a new map to
the Scrum Team. On the vertical axis he draw the probably of a given risk
occurring. On the horizontal axis he draw the impact that the risk will have on
the project or program should it materialize. What map did Tom present to his
team?
Correct answer: C)
You chose: D)
You chose: D)
A)
Risk
burndown
B)
Story
Map
C)
Risk
Map
D)
Value
stream map
Points: 0 out of 1
Feedback:
One of the best ways to visually display risks in a succinct manner is to use a Risk Map. On the vertical axis you have the probably of a given risk occurring, that is, the likelihood that the risk will materialize and become an Issue. On the horizontal axis we have the impact that the risk will have on the project or program should it materialize.
One of the best ways to visually display risks in a succinct manner is to use a Risk Map. On the vertical axis you have the probably of a given risk occurring, that is, the likelihood that the risk will materialize and become an Issue. On the horizontal axis we have the impact that the risk will have on the project or program should it materialize.
Question 36 of 50
Who manages the budget in
Scrum?
Correct answer: C)
You chose: C)
You chose: C)
A)
Top
Management
B)
Scrum
Master
C)
Product
Owner
D)
Project
Manager
Points: 1 out of 1
Feedback:
The product owner leads the development effort to
create a product that generates the desired benefits. This often
includes creating the product vision; grooming the product backlog;
planning the release; involving customers, users, and other
stakeholders; managing the budget; preparing the product launch;
attending the Scrum meetings; and collaborating with the team.
The product owner leads the development effort to
create a product that generates the desired benefits. This often
includes creating the product vision; grooming the product backlog;
planning the release; involving customers, users, and other
stakeholders; managing the budget; preparing the product launch;
attending the Scrum meetings; and collaborating with the team.
Question 37 of 50
Who is responsible for
communicating progress, and managing the stakeholders in Scrum?
Correct answer: D)
You chose: A)
You chose: A)
A)
Both
Scrum Master and Product Owner
B)
Scrum
Master
C)
Team
D)
Product
Owner
Points: 0 out of 1
Feedback:
The product owner is responsible for managing the
release scope and date, managing the budget, communicating progress, and managing the stakeholders.
The product owner is responsible for managing the
release scope and date, managing the budget, communicating progress, and managing the stakeholders.
Question 38 of 50
You were assigned as a
Proxy Product Owner in a Scrum Team. What less likely will you expect to see as
the Project goes on?
Correct answer: D)
You chose: A)
You chose: A)
A)
Increase
in conflicts and miscommunication
B)
Slowdown
in decision making
C)
Decrease
in productivity
and morale
and morale
D)
Increase
in productivity
and morale
and morale
Points: 0 out of 1
Feedback:
The actual product owner ultimately decides about product backlog prioritization, release planning, and whether to accept or reject work results. The sequences of having a proxy Product Owner may include: an increase in conflicts and communication, a slowdown in decision making, and a decrease in productivity and morale.
The actual product owner ultimately decides about product backlog prioritization, release planning, and whether to accept or reject work results. The sequences of having a proxy Product Owner may include: an increase in conflicts and communication, a slowdown in decision making, and a decrease in productivity and morale.
Question 39 of 50
Scrum mandates the backlog
items to be described as:
Correct answer: D)
You chose: D)
You chose: D)
A)
User
Stories
B)
User
Cases
C)
Test-cases
D)
Scrum
does not mandate how product backlog items should be described
Points: 1 out of 1
Feedback:
Scrum does not mandate how product backlog items shouldbe described, but many Scrum teams prefer to work with user stories. As its name suggests, a user story tells a story about a customer or user employing the product. It contains a name, a brief narrative, and acceptance criteria, conditions that must hold true for the story to be complete.
Scrum does not mandate how product backlog items shouldbe described, but many Scrum teams prefer to work with user stories. As its name suggests, a user story tells a story about a customer or user employing the product. It contains a name, a brief narrative, and acceptance criteria, conditions that must hold true for the story to be complete.
Question 40 of 50
What is the best approach
in handling the Product Backlog if you are working on the project with multiple
Scrum teams?
Correct answer: B)
You chose: B)
You chose: B)
A)
Create
component-specific Product Backlogs for each team
B)
Employ
one Product Backlog,
extend the grooming horizon, and consider providing team-specific views into the backlog
extend the grooming horizon, and consider providing team-specific views into the backlog
C)
Prefer
component teams to feature teams and empty separate Product Backlog for each
team
D)
There
is no best approach, it is possible to go with any of them
Points: 1 out of 1
Feedback:
Whenever you work on a large Scrum project, ensure that there is
one product backlog that contains the work necessary to bring the
product to life. Avoid team- or component-specific backlogs that
translate product requirements into subsystem or component
requirements. Employ one product backlog, extend the grooming horizon, and consider providing team-specific views into the backlog.
Whenever you work on a large Scrum project, ensure that there is
one product backlog that contains the work necessary to bring the
product to life. Avoid team- or component-specific backlogs that
translate product requirements into subsystem or component
requirements. Employ one product backlog, extend the grooming horizon, and consider providing team-specific views into the backlog.
Question 41 of 50
What is true regarding
Grooming Horizon on large Scrum Projects?
Correct answer: A)
You chose: A)
You chose: A)
A)
Grooming
horizon increases
B)
Grooming
horizon decreases
C)
Grooming
horizon doesn't change
D)
No
Grooming is performed on large Scrum projects
Points: 1 out of 1
Feedback:
Product backlog items are still decomposed and refined just in time
on large Scrum projects. But the grooming horizon changes. Rather
than focusing on the subsequent sprint, large projects look ahead to
the next two to three sprints when preparing the product backlog
Product backlog items are still decomposed and refined just in time
on large Scrum projects. But the grooming horizon changes. Rather
than focusing on the subsequent sprint, large projects look ahead to
the next two to three sprints when preparing the product backlog
Question 42 of 50
Are the Teams required to
have a release plan in Scrum?
Correct answer: D)
You chose: A)
You chose: A)
A)
Yes,
they are required
B)
It
depends
C)
The
question is incorrect
D)
No,
they are not required
Points: 0 out of 1
Feedback:
Teams are not required to have a release plan in Scrum, but they certainly have to plan the release.
Teams are not required to have a release plan in Scrum, but they certainly have to plan the release.
Question 43 of 50
What is the main purpose
of the Burndown Chart?
Correct answer: A)
You chose: A)
You chose: A)
A)
Inspect
team's progress on a daily basis and adapt its work accordingly
B)
Use
as report in status meetings
C)
Use
as a document for senior management
D)
Inspect
team's progress towards a release
Points: 1 out of 1
Feedback:
The Burndown Chart's primary purpose is to help the team inspect
its progress on a daily basis and adapt its work accordingly. It is not a
status report. Using the sprint burndown as a reporting tool turns it
into a control mechanism.
The Burndown Chart's primary purpose is to help the team inspect
its progress on a daily basis and adapt its work accordingly. It is not a
status report. Using the sprint burndown as a reporting tool turns it
into a control mechanism.
Question 44 of 50
Once an organization has
selected a project or a contract is signed to perform a project, the project
charter must be created. It is signed by the:
Correct answer: C)
You chose: C)
You chose: C)
A)
The
Product Owner
B)
The
Project Manager
C)
The
Senior Management
D)
The
Scrum Master
Points: 1 out of 1
Feedback:
It is signed by the performing organization's senior management.
It is signed by the performing organization's senior management.
Question 45 of 50
What measure will you most
likely use for calculating the velocity of the Team?
Correct answer: B)
You chose: B)
You chose: B)
A)
Ideal
Hours
B)
Story
Points
C)
Elapsed
Hours
D)
Man-hours
Points: 1 out of 1
Question 46 of 50
The minimum plan necessary
to start a Scrum project consists of:
Correct answer: B)
You chose: C)
You chose: C)
A)
A
Release Plan and a Product Backlog
B)
A
Vision and a Product Backlog
C)
A
Team and a Product Backlog
D)
A
Release Plan and a Sprint Plan
Points: 0 out of 1
Feedback:
The minimum plan necessary to start a Scrum project consists of a Vision and a Product Backlog. The vision describes why the project is being undertaken and what the desired end state is.
The minimum plan necessary to start a Scrum project consists of a Vision and a Product Backlog. The vision describes why the project is being undertaken and what the desired end state is.
Question 47 of 50
What of the following is
required to be used in Scrum:
Correct answer: D)
You chose: D)
You chose: D)
A)
User
Stories
B)
Features
C)
Use
Cases
D)
None
of the above is required
Points: 1 out of 1
Feedback:
User Stories, Features, Use Cases can be successfully used in Scrum, but it's not required. This question refers to the best practices and core of the Scrum that can be found in the Scrum Guide.
User Stories, Features, Use Cases can be successfully used in Scrum, but it's not required. This question refers to the best practices and core of the Scrum that can be found in the Scrum Guide.
Question 48 of 50
What Scrum meeting is
strongly aligned with the Kaizen?
Correct answer: A)
You chose: A)
You chose: A)
A)
Retrospective
Meeting
B)
Planning
Meeting
C)
Review
Meeting
D)
Grooming
Points: 1 out of 1
Feedback:
Kaizen is strongly aligned with Agile in the way it encourages changes from the workers rather than asking management what should be changed. Therefore, it's strongly aligned with Retrospective Meeting in Scrum.
Kaizen is strongly aligned with Agile in the way it encourages changes from the workers rather than asking management what should be changed. Therefore, it's strongly aligned with Retrospective Meeting in Scrum.
Question 49 of 50
The Scrum team has just
performed a stakeholder analysis. Where most likely would it save the
information gathered?
Correct answer: A)
You chose: C)
You chose: C)
A)
In
a stakeholder register
B)
In
an impediment backlog
C)
In
an information radiator
D)
In
a backlog
Points: 0 out of 1
Feedback:
One of the activities that helps is a process known as stakeholder analysis. When performing stakeholder analysis, the stakeholders are identified, and their interest in the project is understood. All of this information is captured in a stakeholder register, which is a simple artifact.
One of the activities that helps is a process known as stakeholder analysis. When performing stakeholder analysis, the stakeholders are identified, and their interest in the project is understood. All of this information is captured in a stakeholder register, which is a simple artifact.
Question 50 of 50
Who is eligible to
initiate a cancellation of the Sprint?
Correct answer: D)
You chose: C)
You chose: C)
A)
The
Development Team
B)
The
Scrum Master
C)
The
Stakeholders
D)
All
answers are correct
Points: 0 out of 1
Feedback:A Sprint can be cancelled before the Sprint time-box is over. Only the Product Owner has the authority to cancel the Sprint, although he or she may do so under influence from the stakeholders, the Development Team, or the Scrum Master.
Useful but please clean them up. Thanks.
ReplyDeletethanks. very helpful
ReplyDeleteChoice of an acute study material was important for me so I chose PMI-ACP Dumps. I went through this informative guide and got an astute knowledge of the field. Now I have passed my PMI Agile Certified Practitioner (PMI-ACP) Exam with the help of PMI-ACP Dumps PDF. I say thanks to Realexamdumps.com for all the help.
ReplyDeleteI always wished to have Microsoft Azure but never attempted. Finally, Pass4sure Microsoft Dumps gave me enough reason to go for this IT exam with confidence. When I checked free demo questions on Dumpspass4sure I got impressed. I could easily pass my exam at the first attempt with Microsoft PDF questions and answers.
ReplyDeleteI give seniority to PMI-ACP dumps question answers over all other source of learning due to its authenticity and preciseness. PMI-ACP study material is reliable and predicable. The method of learning is very straightforward and obvious. I prepared myself from PDF PMI-ACP Dumps and online practice test study material and I got the best result I could get. My recommendation is PMI-ACP dumps
ReplyDeleteThank You for sharing.
ReplyDeletePassed PMI PMI-ACP Exam Dumps 2020!!!
My success is not only because of the hard work that I made but the most of the credit goes to Real PMI-ACP exam dumps. I would not have prepared my exam without the exceptional help from PMI-ACP dumps. The work done by DumpsSure.com deserves appreciations.
Blog link:
https://real-splunk-questions-answers.blogspot.com/
https://real-amazon-questions-answers.blogspot.com/
I will suggest everyone to use PMI-ACP questions and answers which helped me the most to get passed in PMI Agile Certified Practitioner. All the questions were expertly designed and were scholarly answered. Very concise and to the point information about each topic is a unique feature of PMI-ACP Exam Dumps. The support of these experts was scholarly and sincere guidance pushed me to do my best. I hope the whole team at RealExamCollection.com will keep on working with the same potential.
ReplyDeleteIt was really hard to think such a great success without the help of PMI-ACP dumps because I was not having any background knowledge of the field. I liked questions and answers which were full of relevant information. PMI-ACP exam dumps has become my favorite study material.
ReplyDeleteI have just got an unlimited success in my career by earning an SOA-C02 by preparing SOA-C02 Dumps PDF from Dumpsprofessor.com, and it all leads to my increase in worth and position in my organization also recommend you guys be a part of this website to be get fulfilled up to the mark. And Now They Are giving a 30% Discount on All Exams by Using Coupon code " DUP30NY21
ReplyDeleteGreat list of questions that are really useful which helped me pass the exam. I hope you don't mind if I include this list of pmi-acp practice questions in my recommended exams/resources to help people pass. Thanks again for the help :)
ReplyDeleteThanks for sharing this study dump, relly helpful. Your audience might also find useful a google form quiz with full length pmi-acp practice exam to get some practice exam questions under their belt :)
ReplyDelete
ReplyDeletePicking SOA-C02 online test engine from PassExam4Sure I got a comprehensive understanding of all the syllabus topics. It was hard for me to think for SOA-C02 exam but I got courage from this concise study guide. Once I went through SOA-C02 Dumps PDF then nothing was difficult for me.
I was thinking AWS Certified Associate exam a very complicated task to pass but SOA-C02 dumps stuff changed my view about it. I could not have passed my certification without using this material for my preparation. I will put forward to all the candidates who are going to appear in an IT certification.
ReplyDeletePMI-ACP dumps doesn’t bring me only good result but it gave me shrewd understanding of the discipline. This handy PDF description of the contents encompassed the whole subject which is very useful for me in the practical field. I commend RealDumpsCollection for such a useful gift to IT students. My recommendation for all candidates is to choose PMI-ACP dumps and get guarantee for their success.
ReplyDeletehttps://www.29chat.com/read-blog/288_how-i-success-in-adobe-ad0-e117-exam-with-adobe-ad0-e117-practice-exam-questions.html
ReplyDeleteGet Valid SY0-601 Exam dumps Questions Answers
ReplyDeletePrepare for Google Professional-Cloud-Architect exam with our preparation material with full confidence. We offer you 100% real Google Cloud Architect Professional Google Professional-Cloud-Architect exam dumps for your better results. Prepare4Test’s Professional-Cloud-Architect pdf dumps are verified by Google Gurus.
ReplyDelete100% Pass Guarantee is offered by us after Google Associate Cloud Engineer Associate-Cloud-Engineer exam preparation, with Prepare4Test’s exam dumps. You can pass the Associate-Cloud-Engineer exam in the first go with good marks, and it will be easy for you to attempt all Associate-Cloud-Engineer questions.
ReplyDeleteThis platform has improved my trust. I gave the PMI-ACP test on this, happily achieving the highest score in the actual IPMI Agile Certified Practitioner.
ReplyDeletehttps://www.dumpsowner.com/pmi/pmi-acp-exam-dumps.html
Take more exams
ReplyDeleteexam dumps
practice test pdf
practice test free
Pdf test
Practice exam
certification dumps
management designer dumps
Questions answers
Passing this certification exam was a dream https://www.marks4sure.com/SY0-601-exam.html for me and I have finally achieved that. I am extremely thankful to marks4sure.com for providing such benificial info.
ReplyDeleteFor your exam preparation to be effective, you need to take help from practice tests which reflect the real exam like environment.These CompTIA SY0-601 Practice Tests serve the same purpose and make your preparation stand out from other candidates.
ReplyDeletePrepare4Test the best and reliable platform where you can get accurate H11-861 question dumps which will assist you in passing your Huawei Certified Network Professional – Video Conference exam fast.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteMany thanks for sharing such kind of info. It is actually not easy to meet the difficulties to Pass your pfmp Exam Dumps, but if you have valid study material like Real Amazon Exam Questions. No doubt will pending to be successful.
ReplyDeleteHence its only need to get an authentic study material to prepare any of your exam, than nobody can stop you to be successful in your field. Only Valid PMI Exam Dumps can be the cause of your success.
For More Details:-
https://dumpstoday.com/
TestsExpert is the best and reliable platform where you can get accurate SAP C_TFIN22_67 exam dumps which will assist you in passing your SAP Certified Application Associate - Management Accounting with SAP ERP 6.0 EhP7 exam.
ReplyDeleteTry Now: https://www.testsexpert.com/c_tfin22_67
Very nice article. Thanks for sharing this post. Also, check out these articles,
ReplyDeleteData Analytics Courses in Australia
Creative Writing Courses in Chandigarh
Financial Modeling Courses in Dubai
The SAP C_SACS_2308 Exam SACS 2308 dumps is a significant milestone for professionals in the field of SAP Analytics Cloud. This certification assesses a candidate's proficiency in SAP's advanced analytics and planning solutions, covering a broad spectrum of topics such as data modeling, reporting, and planning.
ReplyDeleteEarning the SAP C_SACS_2308 certification is a testament to an individual's expertise in harnessing the power of SAP Analytics Cloud to drive data-driven decision-making within an organization. It validates the ability to design and implement robust analytics solutions, enabling businesses to gain actionable insights from their data.
This certification is highly regarded in the industry, enhancing job prospects and career growth for certified individuals. It signifies a commitment to staying updated with the latest developments in SAP's analytics technology, a crucial aspect of maintaining competitiveness in today's data-driven business landscape.
Moreover, the SAP C_SACS_2308 Exam provides professionals with the knowledge and skills to leverage SAP Analytics Cloud's capabilities effectively, helping organizations make informed decisions, optimize processes, and drive innovation in the modern era of data analytics. Continuous learning and practical experience are essential for maintaining the value of this certification over time.
This comment has been removed by the author.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteAZ-900 Dumps:
ReplyDeleteExcellent Study Material: I couldn't have passed the AZ-900 exam without these dumps. The content is comprehensive, and it helped me understand the concepts clearly. Highly recommended!
Accurate and Up-to-Date: These AZ-900 dumps are spot-on! They covered all the topics I encountered on the exam, and I felt well-prepared. Thanks to Exams4sure for keeping their materials up-to-date.
AZ-900 Dumps
Hey folks, just gotta say, Certs4you's AZ-104 Exam Dumps are a total game-changer! Studying for Azure Admin felt like wandering in a maze, but these dumps were my trusty map. Straightforward, no fluff, just the nuggets I needed to ace that test. It's like having a wise mentor guiding you through the chaos.
ReplyDeleteWhizlabs is the go-to platform for Google Cloud Certified Professional Cloud Architect aspirants. The video course, practice tests, and hands-on labs provide a thorough preparation to excel in designing and managing cloud architectures on GCP. Highly recommended!
ReplyDelete