Question: Which of the following BEST describes ROTI?
|
Options:
|
A. Measure of product backlogs remaining
|
B. Measure of quality of features delivered in
an iteration
|
C. Measure of required effort to deliver in an
iteration
|
D. Measure of effectiveness of the
retrospective meeting
|
|
Explanation : Correct Answer is D. Return on Time
Invested (ROTI) is used to measure the effectiveness of the retrospective
meetings from the team members' perspective.
|
|
Question: Technical debt is the gap between a product's actual cost of
change (CoC) and its optimal CoC. Managing technical debt helps ensure
reliable delivery today and ready adaptation to tomorrow's customer needs.
When can Technical Debt occur?
|
Options:
|
A. During Initial Development
|
B. Ongoing Maintenance
|
C. During enhancement
|
D. During all the above mentioned times
|
|
Explanation : Correct Answer is D. Technical debt
can arise during initial development, ongoing maintenance (keeping a product
at its original state), or enhancement (adding functionality).
|
|
Question: Which of the following is NOT a characteristic of Agile
project manager?
|
Options:
|
A. Manages daily tasks of the team members
|
B. Assumes different leadership styles for
different stages of team formation
|
C. Allows team to self-manage
|
D. Facilitates collaboration
|
|
Explanation : Correct Answer is A. Agile Project
Manager does not manage the daily tasks of team members as teams in Agile are
self organizing.
|
|
Question: For a Retrospective meeting, the seating arrangement should
be such that there is enough space for people to move comfortably. Which of
the following is a preferable seating arrangement for a retrospective
meeting?
|
Options:
|
A. Circle or semicircle of chairs
|
B. Theatre style arrangement
|
C. Tables arranged in U-shape
|
D. Meeting Room
|
|
Explanation : Correct Answer is A. circle or
semicircle of chairs encourages participation because people can see each
other. Classroom or theater-style arrangements stifle participation. Staring
at the back of someone else’s head isn’t conducive to conversation. Tables
can be a physical barrier that becomes a psychological barrier. Avoid rooms
with an immovable conference table in the middle. That big ol’ table will
inhibit creative collaboration. This isn’t a board meeting, after all. Tables
arranged in a U-shape with a big gulf in the middle create distance and make
it hard to move around.
|
Question: If we plan to work in a two-week iterations with thirteen
iterations during the project and the team’s velocity will be twenty story
points or ideal days per iterations, what will the size of the total project
in story points be?
|
Options:
|
A. 13
|
B. 20
|
C. 260
|
D. 200
|
|
Explanation : Correct Answer is C. The size of
the total project will be 13 x 20 = 260 story points
|
|
Question: What does acronym DRY stand for?
|
Options:
|
A. Don't Repeat Yourself
|
B. Don't Reject Yourself
|
C. Do Repeat Yourself
|
D. None of the above
|
|
Explanation : Correct Answer is A. This clever
name for a well-known principle comes from Dave Thomas and Andy Hunt. Don’t
Repeat Yourself is more than just avoiding cut-and-paste coding. Eliminating
duplication decreases the time required to make changes. You need only change
one part of the code. It also decreases the risk of introducing a defect by
making a necessary change in one place but not in another.
|
|
Question: Which of the following technique of Scrum requires that every
slice of functionality created by the developers be complete?
|
Options:
|
A. Team Collaboration
|
B. Sashimi
|
C. Scrum tool
|
D. Ability
|
|
Explanation : Correct Answer is B. Scrum uses the sashimi
technique to require that every slice of functionality created by the
developers be complete. All of the requirements gathering and analysis,
design work, coding, testing, and documentation that constitute a complete
product are required to be completed in every Sprint and demonstrated in the
Sprint increment of functionality. Sprints are kept short enough that the
stakeholders don’t lose interest in the project before the Sprints are
completed. And stakeholders can see that they have an opportunity to redirect
the project at the start of every Sprint to optimize the value they derive
from the project. At the end of every Sprint, stakeholders see new
functionality. Models, requirements, and internal artefacts might be of use
to the developers, but they are never shown to the stakeholders.
|
Question: What is MOST true about Participatory Decision Making?
|
Options:
|
A. It is a technique that involves all the
affected parties
|
B. It is just a meeting with no outcomes
|
C. It only involves the customer and the
Product Manager
|
D. It is a technique based on the wishes of
the Scrum Master
|
|
Explanation : Correct Answer is A. It is a
technique that involves all the affected parties
|
|
Question: Team 1 has been asked to complete work on Item 10 story and
deliver it to Team 2 so that they can initiate work on Item 12 story, which
is dependent on completion of Item 10 story. The leader of Team 1 decides to
insert a buffer that protects the start date on Item 12 story against delays
in the completion of Item 10 story. This buffer is known as,
|
Options:
|
A. Feeding Buffer
|
B. Iteration Buffer
|
C. Story Buffer
|
D. Release Buffer
|
|
Explanation : Correct Answer is A. The Feeding
buffer protects the start date on Item 12 story against delays in the
completion of Item 10 story.
|
|
Question: Sometimes stories are too small. A good approach for tiny
stories, common among Extreme Programming teams, is to combine them into
larger stories that represent from about a half-day to several days of work.
The combined story is given a name and is then scheduled and worked on just like
any other story. Which of the following are NOT examples of small stories?
|
Options:
|
A. Bug Reports
|
B. Bugs
|
C. User Interface Changes
|
D. A & C
|
|
Explanation : Correct Answer is B. A story that
is too small is typically one that the developer says she doesn't want to
write down or estimate because doing that may take longer than making the
change. Bug reports and user interface changes are common examples of stories
that are often too small.
|
|
Question: Which of the following BEST describes Task Board?
|
Options:
|
A. The task board is always a white board
|
B. It is a great tool to show the project
trend
|
C. It serves the dual purpose of giving the
team a convenient mechanism for organizing their work and a way of seeing at
a glance how much work is left.
|
D. Task Boards plot the Velocity
|
|
Explanation : Correct Answer is C. Task Board
serves the dual purpose of giving the team a convenient mechanism for
organizing their work and a way of seeing at a glance how much work is left.
It may not always be a white board, it can be a cork board or cardboard too.
|
Question: Wideband Delphi is a repeatable process that can be used :
|
Options:
|
A. To generate estimate
|
B. To create a story
|
C. For implementation purpose
|
D. To motivate the team
|
|
Explanation : Correct Answer is A. Wideband
Delphi is a technique that is used to generate estimation.
|
|
Question: Which of the following is NOT an attribute of a Good Story?
|
Options:
|
A. Testable
|
B. Large
|
C. Independent
|
D. Negotiable
|
|
Explanation : Correct Answer is B. A good story
has six attributes - Independent, Negotiable, Valuable to users or customers,
Estimatable, Small and Testable
|
Question: A story estimated at one story point actually took two days
to complete. How much does it contribute to velocity when calculated at the
end of the iteration?
|
Options:
|
A. One Point
|
B. Three Points
|
C. Two Points
|
D. Cannot be calculated
|
|
Explanation : Correct Answer is A.
|
|
Question: In the Agile Team Stages of Shu Ha Ri, what does 'Ha' stand
for?
|
Options:
|
A. Break the rule
|
B. Follow the rule
|
C. Be the rule
|
D. None of the above
|
|
Explanation : Correct Answer is A. One good model
for mastering anything (if that’s possible) comes from martial arts. A
martial arts student progresses through three stages of proficiency called
Shu Ha Ri. Shu: Follow the rule. Ha: Break the rule. Ri: Be the rule.
|
Question: What does 'R' stand for in ARCS, a criteria for evaluating
Instructional designs by J.M. Keller?
|
Options:
|
A. Relevance
|
B. Repeatable
|
C. Recording
|
D. Right
|
|
Explanation : Correct Answer is A. J. M. Keller,
an expert in motivation and learning, developed criteria for evaluating
instructional designs. The criteria are Attention, Relevance,
Confidence/Competence, Satisfaction—ARCS for short. Choose activities that
help people stay engaged so they don’t drift off (Attention) and that are
relevant to the goal (Relevance). You want activities that people can
accomplish successfully (Confident/Competence). Finally, make sure activities
fit into the overall design so people think the retrospective is a good use
of their time (Satisfaction).
|
Question: As per the Kano Model of customer satisfaction, which
features are MOST important for the product to be successful?
|
Options:
|
A. Exciters
|
B. Linear Features
|
C. Delighters
|
D. Threshold
|
|
Explanation : Correct Answer is D. Threshold
features are those that must be present in the product for it to be
successful. They are often referred to as must-have features.
|
Question: Which of the following defines the splitting of a story or a
feature into smaller, easier-to-estimate pieces?
|
Options:
|
A. Decomposition
|
B. Disaggregation
|
C. Theme
|
D. Epic
|
|
Explanation : Correct Answer is B. Disaggregation
refers to splitting a story or feature into smaller, easier-to-estimate
pieces. If most of the user stories to be included in a project are in the
range of 2-5 days to develop, it will be very difficult to estimate a single
story that may be 100 days.
|
|
Question: Which of the following is NOT true about Retrospective?
|
Options:
|
A. It helps decide how team will work in the
future
|
B. It helps to reflect and learn from the past
|
C. It allows the team to own and drive their
development process
|
D. It decides who will work on the next project
|
|
Explanation : Correct Answer is D. Retrospective
is a meeting where a team looks back on a past period of work so that they
can learn from their experience and apply this learning to future projects.
|
Question: Affinity Estimating is a technique many teams use to quickly
and easily estimate a large number of user stories. What should be the
minimum size for the items in the Product Backlog?
|
Options:
|
A. 20
|
B. 40
|
C. 8
|
D. 5
|
|
Explanation : Correct Answer is A. •The Affinity
Estimating exercise is best conducted on Product Backlogs larger than 20
items. It is best when you have at least 40 items which allows for groupings
to easily become apparent.
|
Question: Of the listed options, which BEST describes User Stories?
|
Options:
|
A. Support tools for analysis
|
B. IEEE 830
|
C. Use Cases
|
D. Interaction Design Scenarios
|
|
Explanation : Correct Answer is A
|
Question: Which of the following is NOT a principle from the Agile
Manifesto?
|
Options:
|
A. Our highest priority is to satisfy the
customer through early and continuous delivery of valuable software.
|
B. Business people and developers must work
together daily throughout the project.
|
C. Continuous attention to technical
excellence and good design does not enhance agility.
|
D. Working software is the primary measure of
progress.
|
|
Explanation : Correct Answer is C. Continuous
attention to technical excellence and good design enhances agility.
|
|
Question: Which of the following will NOT assist in Critical Problem
solving during the project?
|
Options:
|
A. Ask probing questions
|
B. Use Active Listening
|
C. Use Reflective Listening
|
D. Injecting ideas
|
|
Explanation : Correct Answer is D. During
critical problem solving, you can ask probing questions, use active and
reflective listening, Lead to an answer but one should avoid injecting their
own ideas.
|
Question: What is the successful response option at Conflict Level 1 :
Problem to Solve ?
|
Options:
|
A. Collaboration
|
B. Consensus
|
C. Safety
|
D. A&B
|
|
Explanation : Correct Answer is D. Successful
response options at Level 1 are, Collaboration- Seeking a win-win situation.
Consensus- Learning where every team member’s head is with regard to the
issue and, in time, arriving at a decision everyone can back.
|
|
Question: John and Joseph are working in the same room. John is
programming and Joseph is having some discussion with Kim. John gets to hear
their conversation and gets enough information to know that Joseph has talked
about some idea with Kim. What kind of communication is this referred to as?
|
Options:
|
A. Push Communication
|
B. Osmotic Communication
|
C. Pull Communication
|
D. Active Listening
|
|
Explanation : Correct Answer is B. While writing,
reading, typing, or talking, we pick up traces of the ongoing sounds around
us, using some background listening mode, even though we are not consciously
paying attention. If someone says something interesting, we may perk up and
join the conversation. Otherwise, the sound goes through some background
processing, either just above or just below our conscious level. In some
cases, we register enough about the conversation to be able to develop what
we need directly from memory. Otherwise, we may recall a phrase that was
spoken, or perhaps only that a particular person was discussing a particular
topic. In any case, we can ask about it. This taking in information without
directly paying attention to it is like the process of osmosis, in which one
substance seeps from one system, through a separator, into another. Osmotic
communication further lowers the cost of idea tran sfer.
|
Question: At a Retrospective meeting, a few issues are highlighted by
the team. Who is responsible for solving these issues?
|
Options:
|
A. The Scrum Master
|
B. Product Owner
|
C. Stakeholders
|
D. Team
|
|
Explanation : Correct Answer is D. Agile teams
are self organizing and can find solutions to their problems with ease.
|
|
Your Answer : No option selected.
|
Question: A methodology that is based on solutions or sequences of
steps that is known to work for the discipline is known as,
|
Options:
|
A. Normative
|
B. Rational
|
C. Heuristic
|
D. Participative
|
|
Explanation : Correct Answer is A. Normative
methodologies are based on solutions or sequences of steps known to work for
the discipline. Electrical and other building codes in house wiring are
examples. In software development, one would include state diagram
verification in this category.
|
|
Question: Having problems does not indicate a problem in itself, so
welcome problems because they bring with them the chance for the team to
overcome, grow, and become stronger together." As an Agile Coach, which
are the multiple perspectives to analyse to detect the symptoms for the
problem?
|
Options:
|
A. Process Level
|
B. Quality and Performance Level
|
C. Team dynamics dimension
|
D. All of the above
|
|
Explanation : Correct Answer is D. The multiple perspectives to
analyze are , ? The process level: How are we doing with agile? ? The quality
and performance angle: How can the team produce better? ? The team dynamics
dimension: How can the team become a better team?
|
Question: According to DeMarco, Fragmented knowledge workers may look
busy but a lot of their business is just thrashing. The minimum cost penalty
is :
|
Options:
|
A. 15%
|
B. 10%
|
C. 5%
|
D. 25%
|
|
Explanation : Correct Answer is A. The minimum
cost penalty is 15%.
|
Question: When can a plan be changed in Agile Management?
|
Options:
|
A. At the end of the Iteration
|
B. When we have learned something new
|
C. At the Daily Meeting
|
D. You cannot change once the plan is prepared
|
|
Explanation : Correct Answer is B. In Agile, you
can change the plan when something new is learned or when it is known that a
mistake is to be avoided
|
Question: What is the normal time estimate for a research story?
|
Options:
|
A. 1 day
|
B. 1 hour
|
C. Half an hour
|
D. 1 iteration
|
|
Explanation : Correct Answer is A.
|
Question: What do you mean by Throughput?
|
Options:
|
A. Is the amount of production over time
|
B. Is the number of features the team can
develop in a particular amount of time.
|
C. Is the number of features released during a
Release
|
D. Is the number of defects rectified during a
Release
|
|
Explanation : Correct Answer is B. Throughput is
the number of features the team can develop in a particular amount of time.
|
|
Question: Which of the following documents defines the functional and
non-functional requirements that the system should meet to deliver the
vision, prioritized and estimated?
|
Options:
|
A. Prioritized Sprint
|
B. Vision Box
|
C. Product Backlog
|
D. Sprint Review Meet
|
|
Explanation : Correct Answer is C. The Product
Backlog defines the functional and nonfunctional requirements that the system
should meet to deliver the vision, prioritized and estimated.
|
|
Question: Agile Teams use Planning Poker for estimation. Which of the
following is NOT true about Planning Poker?
|
Options:
|
A. It combines expert opinion, analogy, and
disaggregation into an enjoyable approach to estimating that results in quick
but reliable estimates.
|
B. Participants include all of the developers
on the team
|
C. The team for Planning Poker should not
exceed more than 10 participants
|
D. The highest estimate is considered the
final estimate
|
|
Explanation : Correct Answer is D. If estimates
differ, the high and low estimators explain their estimates.
|
Options: |
A. Displaying Work Breakdown
|
B. Displaying Project Status
|
C. Automated Build Report
|
D. Iteration Planning
|
|
Explanation : Correct Answer is D. Iteration
Planning.
|
Question: The retrospective meeting on previous iteration should last
not more than,
|
Options:
|
A. 30 minutes
|
B. 60 minutes
|
C. 10 minutes
|
D. 5 minutes
|
|
Explanation : Correct Answer is B. The
retrospective meeting on previous iteration should be maximum of one hour.
|
|
|
Question: Spike solutions are small standalone programs that
demonstrate what you’ve learned. Which of the following types of spike will
you use if you need to test an approach to your production code?
|
Options:
|
A. Development Spike
|
B. Design Spike
|
C. Scheduling Spikes
|
D. Iteration Spikes
|
|
Explanation : Correct Answer is B. If you need to
test an approach to your production code, Perhaps you want to see how a
design possibility will work in practice, or you need to see how a
persistence framework will work on your production code.
|
V
Question: DSDM uses MoSCoW technique to create the prioritized
requirements list. In MoSCoW technique, 'M' stands for :
|
Options:
|
A. Medium
|
B. Must Have
|
C. Must Not Have
|
D. Minimum Marketable Features
|
|
Explanation : Correct Answer is B. DSDM
popularized the MoSCoW prioritisation scheme, deriving its name from the
first letters of its labels of “Must…”, “Should…”, “Could…”, “Would like to
have, but not this time.” Under MoSCoW, we have some easier-to-defend
categories. “Must-have” requirements or features are fundamental to the
system; without them, the system does not work or has no value. “Should
have’s” are important--by definition, we should have them for the system to
work correctly; if they are not there, then the work-around will likely be
costly or cumbersome. “Could have’s” are useful net additions that add
tangible value, and “Would like’s” are the “also-ran” requests that are duly
noted--but unlikely to make the cut.
|
|
Question: Which are the three coach styles?
|
Options:
|
A. Teaching, Coaching and Advising
|
B. Coaching, Mentoring and Advising
|
C. Coaching, Informator, Advising
|
D. Mentoring, Teaching and Advising
|
|
Explanation : Correct Answer is A. The three
coach styles are Teaching, Coaching, and Advising.
|
Question: One of your stakeholder is interested in viewing the project
progress but he is not interested in details. Which of the following report
can you share with this stakeholder?
|
Options:
|
A. Weekly demo
|
B. Vision Statement
|
C. Release plan
|
D. Burn up chart
|
|
Explanation : Correct Answer is D. Burn-up chart
is an excellent way to get a bird’s-eye view of the project. It shows
progress and predicts a completion date. Most teams produce a burn-up chart
when they update their release plan.
|
|
Question: Who specifies Acceptance Tests in an Agile Project?
|
Options:
|
A. Customer
|
B. Programmer
|
C. Developer
|
D. Product Manager
|
|
Explanation : Correct Answer is A. Because the
software is being written to fulfil a vision held by the customer, the
acceptance tests need to be specified by the customer. The customer can work
with a programmer or tester to actually create the tests, but minimally the
customer needs to specify the tests that will be used to know when a story
has been correctly developed
|
|
Question: One of your stakeholder wants more detail than the vision
statement provides, but not the overwhelming detail of the release and
iteration plans. Which of the following progress report will you share with
this stakeholder?
|
Options:
|
A. Roadmap
|
B. Status email
|
C. Iteration plan
|
D. Productivity chart
|
|
Explanation : Correct Answer is A. Some
stakeholders may want more detail than the vision statement provides, but not
the overwhelming detail of the release and iteration plans. For these
stakeholders, consider maintaining a document or slide deck that summarizes
planned releases and the significant features in each one.
|
Question: Which of the following defines Elapsed Time?
|
Options:
|
A. Is the same as Ideal Time
|
B. Is the amount of time that passes on a
clock or perhaps a calendar
|
C. Is the amount of time that something takes
when stripped of all peripheral activities
|
D. Is the amount of time the team spent on the
iteration
|
|
Explanation : Correct Answer is B. Elapsed Time
Is the amount of time that passes on a clock or perhaps a calendar.
|
|
|
Question: Feature X has a value of 12 and the total value of all
features is 35. If the feature is estimated to cost 56%, what is the priority
of this feature using relative weighting?
|
Options:
|
A. 0.34
|
B. 0.61
|
C. 1.64
|
D. 0.625
|
|
Explanation : Correct Answer is B. The priority
of the feature is determined by dividing the priority %by the cost %. Hence
the answer = (12/35)/(0.56) = 0.61.
|
Question: How is the Retrospective meeting BEST conducted?
|
Options:
|
A. Set the stage, Gather data, Generate
Insights, Decide on what to do, Close the Retrospective
|
B. Gather data, Generate Insights, Decide on
what to do, Set the stage, Close the Retrospective
|
C. Set the stage, Gather data, Decide on what
to do, Generate Insights, Close the Retrospective
|
D. Decide on what to do, Set the stage, Gather
data, Generate Insights, Close the Retrospective
|
|
Explanation : Correct Answer is A. The correct
sequence is Set the stage, Gather data, Generate Insights, Decide on what to
do, Close the Retrospective
|
50 )Question: Which of the following BEST describes error-feedback
ratio?
|
Options:
|
A. Time spend to fix the hard bugs
|
B. Number of defects corrected in a specific
time
|
C. Number of errors predicted
|
D. Number of new defects injected when fixing
existing defects
|
|
Explanation : Correct Answer is D. Error-feedback
ratio is the number of new defects injected when fixing existing defects
(e.g., 20 new defects generated in fixing 100 defects would be an
error-feedback ratio of 20%).
|
Question: How do you best describe the primary role of an Agile
leader?
|
Options:
|
A. Manage WBS, schedule and cost of project
|
B. Manage stakeholders
|
C. Manage work allocation to team members
|
D. Manage teams without managing their tasks
|
|
Explanation : Correct Answer is D. Agile leaders
do not have to manage the tasks of the team members.
|
|
Your Answer : No option selected.
|
Question: Assuming one-week iterations and a team of four developers,
how many iterations will it take the team to complete a project with 27 story
points if they have a velocity of 4?
|
Options:
|
A. 7
|
B. 4
|
C. 6
|
D. 24
|
|
Explanation : Correct Answer is A. Number of
Iterations = 27/4 = 6.75 ~7
|
|
Your Answer : No option selected.
|
|
|
|
Question: Which of the following is a STORY?
|
Options:
|
A. "Full-screen demo option for job
fair"
|
B. "Automate integration build"
|
C. "Deploy to staging server outside the
firewall"
|
D. "Improve performance"
|
|
Explanation : Correct Answer is A. "Automate
integration build" does not represent customer value, hence not a story.
"Deploy to staging server outside the firewall" describes
implementation details rather than an end result, and it doesn’t use customer
terminology, hence not a story. "Improve performance" has no clear
completion criteria, hence not a story.
|
|
|
|||||||||
Question: Which of the following BEST describes Horizontal Market
Software?
|
|||||||||
Options:
|
|||||||||
A. Developed for many organizations
|
|||||||||
B. Developed and used across many industries
|
|||||||||
C. Developed for a dedicated customer
|
|||||||||
D. Developed for one organization
|
|||||||||
|
|||||||||
Explanation : Correct Answer is B. software
that’s intended to be used across a wide range of industries. The rows of
shrinkwrapped software boxes at your local electronics store are a good
example of horizontal-market software. So are many web sites.
|
|||||||||
|
|||||||||
Question: At the second level of conflict, i.e. Disagreement, Team
members distance themselves from one another to ensure they come out OK in
the end or to establish a position for compromise they assume will come. They
may talk offline with other team members to test strategies or seek advice
and support. What becomes as important as solving the problem?
|
|||||||||
Options:
|
|||||||||
A. Self protection
|
|||||||||
B. Satisfy self ego
|
|||||||||
C. Aim to win
|
|||||||||
D. None of the above
|
|||||||||
|
|||||||||
Explanation : Correct Answer is A. At level 2, self-protection
becomes as important as solving the problem. Team members distance themselves
from one another to ensure they come out OK in the end or to establish a
position for compromise they assume will come. They may talk offline with
other team members to test strategies or seek advice and support.
|
|||||||||
|
|||||||||
Question: What financial return parameter will be BEST for comparing
the values of two different cash flow streams?
|
|||||||||
Options:
|
|||||||||
A. Internal Rate of Return
|
|||||||||
B. Payback Period
|
|||||||||
C. Discounted Payback Period
|
|||||||||
D. Compound Interest
|
|||||||||
|
|||||||||
Explanation : Correct Answer is A. Internal Rate of Return (IRR)
is used to express the return on project in % terms when comparing two
different cash flow streams.
|
|||||||||
|
|||||||||
Your Answer : No option selected.
|
|||||||||
Question: In a Fixed Price contract, the risk is beared by,
|
|||||||||
Options:
|
|||||||||
A. Supplier
|
|||||||||
B. Customer
|
|||||||||
C. Product Owner
|
|||||||||
D. Project Team
|
|||||||||
|
|||||||||
Explanation : Correct Answer is A. Obvious risk is on the side of
the supplier. If the estimates are wrong, the project will lose money. Less
obvious risks are the change request game, through which the supplier
negotiates additional revenue through scope changes. If the supplier had
badly underestimated the effort or risk, or quoted an unrealistically low
price, the losses can even threaten the existence of the supplier, which also
presents a problem to the customer.
|
|||||||||
|
|||||||||
Question: Self-organization implies a reliance on internal motivation
of the team rather than external motivation. This is referred to as,
|
|||||||||
Options:
|
|||||||||
A. Delegatory management
|
|||||||||
B. Measurement based management
|
|||||||||
C. Democratic management
|
|||||||||
D. Autocratic management
|
|||||||||
|
|||||||||
Explanation : Correct Answer is A. Self-organization implies a
reliance on internal motivation of the team rather than external motivation
(i.e., a measurement target). Author Austin calls this delegatory management
as contrasted with measurement-based management. He goes on to say, that
"measurement-based management is in conflict with delegatory management.
There is a negative interaction because of the implicit message of distrust
that a measurement system conveys by the fact of its existence.
|
|||||||||
|
|||||||||
Question: A meeting where a team looks back on a past period of work
so that they can learn from their experience and apply this learning to
future projects is popularly known as?
|
|||||||||
Options:
|
|||||||||
A. Retrospective
|
|||||||||
B. Sprint Planning Meeting
|
|||||||||
C. Sprint Review Meeting
|
|||||||||
D. Status Meeting
|
|||||||||
|
|||||||||
Explanation : Correct Answer is A. Retrospective is the meeting
where a team looks back on a past period of work so that they can learn from
their experience and apply this learning to future projects.
|
|||||||||
Question: Who performs Value Point estimating?
|
|||||||||
Options:
|
|||||||||
A. Finance Team
|
|||||||||
B. Scrum Team
|
|||||||||
C. Product Team
|
|||||||||
D. Development Team
|
|||||||||
|
|||||||||
Explanation : Correct Answer is C. Value Point estimation is done
by the Product Team.
|
|||||||||
|
Question:
Who performs Value Point estimating?Options:A. Finance
TeamB. Scrum TeamC. Product TeamD. Development Team Explanation
: Correct Answer is C. Value Point estimation is done by the Product
Team. Your Answer : No option selected.
|
|||||||||||
Question: Which of the following tests verify that units and
combinations of units work together to perform the desired operations?
|
|||||||||||
Options:
|
|||||||||||
A. Unit tests
|
|||||||||||
B. Component tests
|
|||||||||||
C. Exploratory Tests
|
|||||||||||
D. Usability tests
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. Component
tests verify that units and combinations of units work together to perform
the desired operations.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: In absence of the Product Owner, who should assume the
Product Owner's responsibilities at the Sprint planning meeting?
|
|||||||||||
Options:
|
|||||||||||
A. Scrum Master
|
|||||||||||
B. Team
|
|||||||||||
C. Person selected by the Product Owner
|
|||||||||||
D. Person selected by the team
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. When the Product Owner is not
present, the Scrum Master will take on the responsibility to prepare Product
Backlog for the Sprint planning meeting.
|
|||||||||||
|
|||||||||||
Question: Which of the following is NOT included in the 'Story cards
information'?
|
|||||||||||
Options:
|
|||||||||||
A. Estimated Value Points
|
|||||||||||
B. Story description
|
|||||||||||
C. Story dependencies
|
|||||||||||
D. Velocity
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Story cards information
include Story name, Story description, Estimated work effort, Estimated value
points, Requirements uncertainty, Story dependencies, Acceptance tests.
Velocity is a measure of a team's rate of progress per iteration.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: A Retrospective can be as short as 15 minutes or as long as
1 hour. The duration of the Retrospective can be dependent on all of the
following EXCEPT :
|
|||||||||||
Options:
|
|||||||||||
A. Length of the Iteration
|
|||||||||||
B. Level of conflict or controversy
|
|||||||||||
C. Size of the team
|
|||||||||||
D. Seniority of the Product Owner
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Of all the listed options, the
length of the Retrospective is not dependent on the seniority of the product
owner. The length of the retrospective can be dependent on Length of
Iteration, Level of conflict or controversy, size of the team and complexity
(of technology, organization of the team, relationships with external
department)
|
|||||||||||
|
|||||||||||
Question: Which of the following correctly defines 'Quantity of
Function'?
|
|||||||||||
Options:
|
|||||||||||
A. Scope measured in terms of user stories, use cases,
requirements, or features
|
|||||||||||
B. Expressed as functionality produced for the time and effort
|
|||||||||||
C. Expressed in terms of defect rate
|
|||||||||||
D. Amount of effort expended in person-months
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. Quantity of function is,
scope, measured in terms of user stories, use cases, requirements, or
features (depending on a particular situation). In software, these may be
measured ultimately as objects, modules, classes, or lines of code.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
Question: In a complete Product Planning structure, which of the
following denotes the product planning structure with a medium range
timeframe, story level of detail and capability commitment?
|
Options:
|
A. Release
|
B. Story
|
C. Roadmap
|
D. Wave
|
|
Explanation : Correct Answer is D. Wave is the
Product Planning structure with Medium range time frame (3 months) with Story
level capability and Capability commitment.
|
|
Your Answer : No option selected.
|
Question: What are the four key terms by which the iterative part of
Agile is defined?
|
Options:
|
A. timeboxed, releasable, agility and
incremental
|
B. Iterative, feature-based, timeboxed, and
incremental
|
C. Feature-based, timeboxed, agility and
incremental
|
D. None of the above
|
|
Explanation : Correct Answer is B. Iterative
development means that we build a partial version of a product and then
expand that version through successive short time periods of development
followed by reviews and adaptations. Feature-based delivery means that the
engineering team builds features of the final product or, particularly with
industrial products, at least a close representation of the final product
(such as a simulation model). Iterations are constrained to produce a result
within a certain period of time—a timebox (as short as 1–4 weeks for
software). Timeboxes force closure; they force us to make something concrete,
often before we are quite ready. Incremental development means that we build
these products such that they could be deployed at the end of one or more of
the iterations.
|
|
Question: Which of the following statements are NOT TRUE regarding
Agility?
|
Options:
|
A. Agility is the ability to balance
flexibility and stability
|
B. Agility is the ability to both create and
respond to change in order to profit in a turbulent business environment
|
C. Agility is avoiding planning and lack of
structure
|
D. Agility is ability to deliver customer
value while dealing with inherent project unpredictability and dynamism
|
|
Explanation : Correct Answer is C. Agility is the
ability to both create and respond to change in order to profit in a
turbulent business environment. It is the ability to balance flexibility and
stability.
|
|
Your Answer : No option selected.
|
Question: There are different types of Retrospectives. These are
Release Retrospectives, Project Retrospectives, Iteration Retrospectives and
Surprise Retrospectives. What are Surprise Retrospectives?
|
|||||||||||
Options:
|
|||||||||||
A. Is conducted when an unexpected event
changes your situation
|
|||||||||||
B. Is conducted at the end of each Iteration
|
|||||||||||
C. Is conducted half way of each project
|
|||||||||||
D. Is suggested by the Scrum Master
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. Surprise
Retrospective is conducted when an unexpected event changes your situation.
It gives you a chance to reflect more deeply on your experiences and condense
key lessons to share with the rest of the organization.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: If your release is 12 iterations away, your velocity is 14
points, your risk exposure is one iteration and with a 10% chance, how many
points will you have finished?
|
|||||||||||
Options:
|
|||||||||||
A. 154
|
|||||||||||
B. 110
|
|||||||||||
C. 86
|
|||||||||||
D. 92
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. Using the following formula,
risk_adjusted_points_remaining = (iterations_remaining - risk_exposure) *
velocity / risk_multiplier --> points remaining = (12 - 1) * 14 = 154
points 10 percent chance: 154 / 1 = 154 points.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following reports visually shows the remaining
estimated workload over the course of the project?
|
|||||||||||
Options:
|
|||||||||||
A. Product Backlog Burndown Report
|
|||||||||||
B. Gantt Chart
|
|||||||||||
C. Product Backlog
|
|||||||||||
D. Sprint Chart
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. The Product Backlog Burndown
report graphs remaining estimated workload over the course of the project.
Workload at the start of each Sprint is measured by summing all open Product
Backlog work estimates.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Every team needs to constantly evaluate and make appropriate
adaptations in the following four areas:
|
|||||||||||
Options:
|
|||||||||||
A. Product value, Product quality, Team performance, Project
status
|
|||||||||||
B. Product value, Product quality, Team performance, Organization
status
|
|||||||||||
C. Product quality, Team performance, Project status, Project
deliverables
|
|||||||||||
D. Product value, Product Features, Team performance, Project
status
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. Every team needs to constantly
evaluate and make appropriate adaptations in the following four areas:
Product value, Product quality, Team performance, Project status
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: What is the BEST tool for tracking the progress of the
project and evaluating the ROI?
|
|||||||||||
Options:
|
|||||||||||
A. Sprint Backlog
|
|||||||||||
B. Product Backlog
|
|||||||||||
C. Iteration Backlog
|
|||||||||||
D. None of the above
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following is NOT true about Kanban ?
|
|||||||||||
Options:
|
|||||||||||
A. A Kanban System visualises some unit of value, such as User
Story, Minimal Marketable Feature or Plain Old Requirement
|
|||||||||||
B. A Kanban System manages the flow of these units of value,
through the use of Work In Process limits.
|
|||||||||||
C. Kanban is same as a Task Board
|
|||||||||||
D. It is a key tool in Lean Manufacturing
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is C. A Kanban System visualises
some unit of value. This unit of value could be a User Story, Minimal
Marketable Feature, Plain Old Requirement or something else. This is
different from a task-board, which generally focuses on visualising the
current tasks.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: What is the relative contribution of feature X to the
project if it has a value of 12 and the total value of all features is 35?
|
|||||||||||
Options:
|
|||||||||||
A. 0.38
|
|||||||||||
B. 0.34
|
|||||||||||
C. 2.91
|
|||||||||||
D. 14.91
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. To calculate the relative
contribution of each feature, divide its value by the sum of the Total Value
of all features. Hence, relative contribution of feature X = 12/35 = 0.34.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: What is the relative contribution of feature X to the
project if it has a value of 12 and the total value of all features is 35?
|
|||||||||||
Options:
|
|||||||||||
A. 0.38
|
|||||||||||
B. 0.34
|
|||||||||||
C. 2.91
|
|||||||||||
D. 14.91
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. To calculate the relative
contribution of each feature, divide its value by the sum of the Total Value
of all features. Hence, relative contribution of feature X = 12/35 = 0.34.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: What is the process of defining and prioritizing the
nonfunctional requirements for scaling known as?
|
|||||||||||
Options:
|
|||||||||||
A. Decomposition
|
|||||||||||
B. Staging
|
|||||||||||
C. Stanking
|
|||||||||||
D. Prioritizing
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. The process of defining and
prioritizing the nonfunctional requirements for scaling is called staging.
Staging occurs prior to the start of the first Sprint and takes just one day.
During this day, the nonfunctional scaling requirements for this particular
project are determined and placed in the Product Backlog.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: You have been assigned a New Project that is large, complex
and uncertain. As a Project Manager, you will be using agile project
management. Which of the following will you select while creating your team?
|
|||||||||||
Options:
|
|||||||||||
A. Team is expandable with the project
|
|||||||||||
B. Large Team
|
|||||||||||
C. Functional Manager is responsible for the team
|
|||||||||||
D. None of the above
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. As per Agile methodology, it
is best to work with small teams staffed by talented and experienced people
and increase the number only when required.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Team A finished 43 story points in their last two-week
iteration. Team B is working on a separate project and has twice as many
developers. They also completed 43 story points in their last two-week
iteration. What can you infer from this?
|
|||||||||||
Options:
|
|||||||||||
A. The story points of one team are not comparable to the story
points of any other team.
|
|||||||||||
B. Team A is twice as productive as Team B.
|
|||||||||||
C. Team A should have more people on the team
|
|||||||||||
D. Team B has the management support
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. The story points of one team
are not comparable to the story points of any other team.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Who should participate in Iteration Planning?
|
|||||||||||
Options:
|
|||||||||||
A. Customer, Iteration Manager, Developers, Testers
|
|||||||||||
B. Product Manager, Iteration Manager, Developers, Testers
|
|||||||||||
C. Entire Project Team
|
|||||||||||
D. Product Specialists, Customer, Iteration Manager, Developers,
Testers
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is C. The entire project
team—product manager, product specialists, customers, developers, testers,
iteration manager, project leader—should participate in the iteration
planning session as it provides everyone with the context for work to be
accomplished during the iteration. Functional manager participation can help
the team better understand strategic priority issues and demonstrates
commitment to and support of the project.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following is NOT a Closed Story?
|
|||||||||||
Options:
|
|||||||||||
A. A recruiter can review resumes from applicants to one of her
ads.
|
|||||||||||
B. A recruiter can delete an application that is not a good match
for a job.
|
|||||||||||
C. A recruiter can manage the ads she has placed
|
|||||||||||
D. A recruiter can change the expiration date of an ad
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is C. "A recruiter can manage
the ads she has placed." This is not a closed story: Managing the ads
she's placed is not something that is ever completely done. Instead, it is an
ongoing activity.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following is NOT a Closed Story?
|
|||||||||||
Options:
|
|||||||||||
A. A recruiter can review resumes from applicants to one of her
ads.
|
|||||||||||
B. A recruiter can delete an application that is not a good match
for a job.
|
|||||||||||
C. A recruiter can manage the ads she has placed
|
|||||||||||
D. A recruiter can change the expiration date of an ad
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is C. "A recruiter can manage
the ads she has placed." This is not a closed story: Managing the ads she's
placed is not something that is ever completely done. Instead, it is an
ongoing activity.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: A technique defined by Dean Leffingwell and Don Widrig for
use cases is also used for Prioritization. This is a voting scheme where each
stakeholder is given 100 points that he or she can use for voting in favour
of the most important requirements. How they distribute the 100 points is up
to them: 20 here, 10 there or even all 100 on a single requirement if that is
their sole priority. This method is known as:
|
|||||||||||
Options:
|
|||||||||||
A. Monopoly Money
|
|||||||||||
B. 100-Point method
|
|||||||||||
C. Requirements Prioritization Money
|
|||||||||||
D. Agile Prioritization
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. The 100-Point Method was
originally developed by Dean Leffingwell and Don Widrig for use cases and is
used for prioritization as well. It is a voting scheme where each stakeholder
is given 100 points that he or she can use for voting in favour of the most
important requirements. How they distribute the 100 points is up to them: 20
here, 10 there or even all 100 on a single requirement if that is their sole
priority.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following is NOT done as part of Planning in
Agile Project Management?
|
|||||||||||
Options:
|
|||||||||||
A. Risk Management
|
|||||||||||
B. Product Vision
|
|||||||||||
C. Slack
|
|||||||||||
D. Done - Done
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Done-Done is part of
releasing.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following correctly defines the role of the
Scrum Master?
|
|||||||||||
Options:
|
|||||||||||
A. Achieves initial and ongoing funding for the project by
creating the project’s initial overall requirements
|
|||||||||||
B. Is responsible for the Scrum process, for teaching Scrum to
everyone involved in the project
|
|||||||||||
C. Is responsible for developing the functionality
|
|||||||||||
D. Is responsible for the Product Backlog
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. The ScrumMaster is responsible
for the Scrum process, for teaching Scrum to everyone involved in the
project, for implementing Scrum so that it fits within an organization’s
culture and still delivers the expected benefits, and for ensuring that
everyone follows Scrum rules and practices.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: In XP, the code goes through four levels of completion.
Which of the following states the right sequence?
|
|||||||||||
Options:
|
|||||||||||
A. Broken, Build, Ready for demo, Ready to release
|
|||||||||||
B. Build, Ready for demo, Broken, Ready to release
|
|||||||||||
C. Build, Ready for demo, Ready to release, Broken
|
|||||||||||
D. Broken, Build, Ready to release, Ready for demo
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. your code goes through four
levels of completion: 1. Broken. This only happens in your sandbox. 2. Builds
and passes all tests. All versions in your repository are at least at this
level. 3. Ready to demo to stakeholders. Any version marked with the
“Iteration X" tag is ready for stakeholders to try. 4. Ready to release
to real users and customers. Any version marked with the “Release Y" tag
is production ready.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following is NOT a technique for estimating a
story?
|
|||||||||||
Options:
|
|||||||||||
A. Expert Opinion
|
|||||||||||
B. Analogy
|
|||||||||||
C. Disaggregation
|
|||||||||||
D. Decomposition
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Decomposition is not a
technique for estimating.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: An informative workspace broadcasts information into the
room. Of the following, which does NOT constitute to Informative workspace?
|
|||||||||||
Options:
|
|||||||||||
A. Big Visible Charts
|
|||||||||||
B. Process Improvement Charts
|
|||||||||||
C. Hand Drawn Charts
|
|||||||||||
D. SRS Document
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. An informative workspace
broadcasts information into the room. Examples are Big Visible Charts,
Process Improvement Charts, Hand Drawn Charts and others
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: When a group of people come together as a team, they go
through a specific sequence of group dynamics. Which of the following depicts
the correct sequence?
|
|||||||||||
Options:
|
|||||||||||
A. Forming, Norming, Performing, Storming
|
|||||||||||
B. Forming, Storming, Norming, Performing
|
|||||||||||
C. Forming, Performing, Storming, Norming
|
|||||||||||
D. Storming, Norming, Performing, Forming
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Forecasting the Financial value of a theme is the
responsibility of,
|
|||||||||||
Options:
|
|||||||||||
A. Analysts
|
|||||||||||
B. Product Owner
|
|||||||||||
C. Project Manager
|
|||||||||||
D. All Team Members
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Forecasting the financial
value of a theme is the responsibility of the product owner but it is a
responsibility shared with all other team members—programmers, testers,
analysts, project managers, and so on.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following is NOT true regarding Scope in Agile
Projects?
|
|||||||||||
Options:
|
|||||||||||
A. Scope management in agile is primarily a function of
"rolling wave" planning and the management of the product backlog.
|
|||||||||||
B. "Scope creep" doesn't exist in agile projects,
because scope is expected to change
|
|||||||||||
C. Scope is controlled through the use of the backlog, rolling
wave planning, and the protection of the iteration.
|
|||||||||||
D. Scope is verified by the Product manager, who is responsible
for accepting or rejecting the features completed each iteration.
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Scope is verified by the
customer, who is responsible for accepting or rejecting the features
completed each iteration.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: When should be the BEST time for the team to estimate a
task?
|
|||||||||||
Options:
|
|||||||||||
A. Throughout the Iteration
|
|||||||||||
B. During Iteration Planning
|
|||||||||||
C. Task estimates are decided by the Scrum Master
|
|||||||||||
D. At the time of Iteration Planning as well as during the
iteration
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Project Team will estimate a
task at the time of Iteration Planning as well as during the iteration
planning.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: A long term plan of action designed to achieve a particular
goal is referred to as,
|
|||||||||||
Options:
|
|||||||||||
A. Tactical Planning
|
|||||||||||
B. Strategic Planning
|
|||||||||||
C. Goal Planning
|
|||||||||||
D. Roadmap Planning
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. strategy is a long-term plan
of action designed to achieve a particular goal. A tactic is a method
employed to achieve a certain goal. The goal pursued by strategic planning is
at a higher level of abstraction than the goals pursued by tactics.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected
|
|||||||||||
Question: The Levels of Listening by Whitworth states 3 Levels of
listening. What does the third level, viz. Global listening refer to?
|
|||||||||||
Options:
|
|||||||||||
A. A hardwired connection is established between the coach and
the speaker
|
|||||||||||
B. The coach uses everything in the environment. Viz. speaker's
tone of voice, posture, etc when listening at this level
|
|||||||||||
C. The coach hears the speaker's words attentively
|
|||||||||||
D. The coach only hears the global sounds and not the speaker's
words
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. The coach uses everything in
the environment when listening at Level III. The speaker’s tone of voice,
posture, changes in room temperature, what noises are happening around
them—all of these things are noticed and used by the coach.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following are MOST helpful in implementing
collective code ownership in a team?
|
|||||||||||
Options:
|
|||||||||||
A. Version control
|
|||||||||||
B. Pair programming
|
|||||||||||
C. Continuous integration
|
|||||||||||
D. Probability distribution
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: The primary task in release planning is assigning stories to
iterations, chiefly on the basis of _______________________
|
|||||||||||
Options:
|
|||||||||||
A. Value and Risk
|
|||||||||||
B. Risk and Priority
|
|||||||||||
C. Customer Requirements
|
|||||||||||
D. Team ability and Value
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. The primary task in release
planning is assigning stories to iterations, chiefly on the basis of value
and risk.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: What is Stress Testing?
|
|||||||||||
Options:
|
|||||||||||
A. Ensures that all of the components of the user interface
behave as expected
|
|||||||||||
B. Is done to ensure an application that can be easily used
|
|||||||||||
C. Is done to gauge how well the application will perform under
various workloads
|
|||||||||||
D. Where the application is subjected to extreme values of users,
transactions, or anything else that may put the application under stress
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Stress Testing is where the
application is subjected to extreme values of users, transactions, or
anything else that may put the application under stress.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: For projects of similar size and type, projects that that
have a cumulative defect removal rate at the nodal point, have the shortest
schedules, have the lowest quantity of effort in terms of person-months, and
have the highest levels of user satisfaction after release. What is this
nodal point?
|
|||||||||||
Options:
|
|||||||||||
A. 15%
|
|||||||||||
B. 95%
|
|||||||||||
C. 35%
|
|||||||||||
D. 50%
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. Capers Jones' widely heralded
book on software measurement concluded that "a cumulative defect removal
rate of 95% on a project appears to be a nodal point where several other
benefits accrue". For projects of similar size and type, these projects
have the shortest schedules, have the lowest quantity of effort in terms of
person-months, and have the highest levels of user satisfaction after
release.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: During which project management phase are the product
stories delivered?
|
|||||||||||
Options:
|
|||||||||||
A. Envision
|
|||||||||||
B. Speculate
|
|||||||||||
C. Explore
|
|||||||||||
D. Adapt
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. During the Speculate phase,
the product stories are delivered. This phase involves planning and
delivering tested stories in a short iteration, constantly seeking to reduce
the risk and uncertainty of the project.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: What is the outcome of a Sprint Planning Meeting?
|
|||||||||||
Options:
|
|||||||||||
A. Sprint Backlog
|
|||||||||||
B. Product Backlog
|
|||||||||||
C. Iteration Backlog
|
|||||||||||
D. None of the above
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. The outcome of Sprint Planning
meeting is the Sprint Backlog.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following correctly defines the Complex Story?
|
|||||||||||
Options:
|
|||||||||||
A. A User Story that comprises of multiple shorter stories
|
|||||||||||
B. A User Story that that users can mark as inactive
|
|||||||||||
C. User story that is inherently large and cannot easily be
disaggregated into a set of constituent stories.
|
|||||||||||
D. It is not a Story
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is C. Epics typically fall into two
categories - Compound Stories and Complex Stories. the complex story is a
user story that is inherently large and cannot easily be disaggregated into a
set of constituent stories.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: In the design-the-box activity, the entire team, including
product team members customers, breaks into groups of four to six people.
Their task is to design the product box—front and back. Which of the
following is NOT Included ?
|
|||||||||||
Options:
|
|||||||||||
A. Graphic
|
|||||||||||
B. Feature Description
|
|||||||||||
C. Operating Requirements
|
|||||||||||
D. Competitor's product name and features
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. In the design-the-box
activity, the entire team, including product team members customers, breaks
into groups of four to six people. Their task is to design the product
box—front and back. This involves coming up with a product name, a graphic,
three to four key bullet points on the front to "sell" the product,
a detailed feature description on the back, and operating requirements.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: You are part of the team that developed software for the
organization's own use in serving the hospital customers. At one point, the
CEO realizes that with some enhancements the software could be used to provide
the same services to health insurers. The team is asked to make the changes
and is able to bring an entirely new source of revenue into the company
because of what the new software enabled. Under what revenue stream is this
feature classified?
|
|||||||||||
Options:
|
|||||||||||
A. New Revenue
|
|||||||||||
B. Incremental Revenue
|
|||||||||||
C. Retained Revenue
|
|||||||||||
D. Operational Efficiencies
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is A. New Revenue is the return on
the project due to a new opportunity.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected
|
|||||||||||
Question: Which of the following explains 'Retained Revenue'?
|
|||||||||||
Options:
|
|||||||||||
A. revenue due to a new opportunity
|
|||||||||||
B. additional, incremental revenue from existing customers
|
|||||||||||
C. revenue an organization will lose if the project is not
performed.
|
|||||||||||
D. Option A and C
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is C. Retained revenue refers to the
revenue an organization will lose if the project is not performed.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which of the following explains 'Retained Revenue'?
|
|||||||||||
Options:
|
|||||||||||
A. revenue due to a new opportunity
|
|||||||||||
B. additional, incremental revenue from existing customers
|
|||||||||||
C. revenue an organization will lose if the project is not
performed.
|
|||||||||||
D. Option A and C
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is C. Retained revenue refers to the
revenue an organization will lose if the project is not performed.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: What are the planning horizons in the planning onion that
the agile teams are majorly involved in an Agile project?
|
|||||||||||
Options:
|
|||||||||||
A. Strategy, Portfolio, Product
|
|||||||||||
B. Product, Release, Iteration
|
|||||||||||
C. Release, Iteration, Day
|
|||||||||||
D. Product, Iteration, Day
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is C. Most agile teams are only
concerned with the three innermost levels of the planning onion, i.e.
Release, Iteration and Day.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
|
|||||||||||
Question: In a project, all of the user stories
are estimated and the sum of those estimates is 100 story points. Based on
past experience, it is known that the team’s velocity is 9 story points per
two-week iteration. How many iterations does the project need to complete the
user stories?
|
|||||||||||
Options:
|
|||||||||||
A. 9
|
|||||||||||
B. 11
|
|||||||||||
C. 1
|
|||||||||||
D. 90
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is B. Iterations =
100/9 = 11.1
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
Question: Which report should NOT be shared with your stakeholders?
|
|||||||||||
Options:
|
|||||||||||
A. Defect reports
|
|||||||||||
B. Status reports
|
|||||||||||
C. Throughput reports
|
|||||||||||
D. SLOC reports
|
|||||||||||
|
|||||||||||
Explanation : Correct Answer is D. Source Lines of Code (SLOC)
reports should not be shared with the stakeholders, as they are flawed
productivity metrics.
|
|||||||||||
|
|||||||||||
Your Answer : No option selected.
|
|||||||||||
|
|||||||||||
|
|||||||||||
|
|||||||||||
|
|||||||||||
|
|||||||||||
|
|||||||||||
|
|||||||||||
|
|||||||||||
|
Would help if questions were numbered, then one could provide feedback as to where the same question repeats itself, where the answer is a bit "flawed" or simply spelling mistakes or formatting issues. Globally, the process was OK, would have appreciated have the answers available on a separate page so that one could answer the questions and then view the answers. Many thanks though, was a great help
ReplyDeletePassed in my second attempt and lucky to find 360pmo braindumps. Wish you all good luck in attempting ACP
ReplyDeletehttp://www.360pmo.com/home/products/pmi-acp-full-length-practice-exam/
Mike: im also preparing acp exam.. can u plz suggest me which mock exam i ll prefer..
DeleteI got 79% in above 120 question and planning to give exam now.. Many question were NEW to me.
ReplyDeleteBut still i feel confident for exam..
Thanks a bunch!
ReplyDeleteGood set of questions. Useful for PMI-ACP definitely. Suggest the following:
ReplyDelete1. Avoid duplicate questions (a few are duplicates)
2. The formatting has gone heywire inbetween
3. Suggest to hide the answers and show upon click for each question as otherwise we invariably see some answers when scrolling down.
Appreciate the great effort! Could also include a paid version
That helped... Thanks a lot!!!
ReplyDeleteThis is really an incredible resource! Thank you for taking the time and sharing. You can also check out this PMI-ACP Study Guide for some positive reinforcement. Good luck!
ReplyDeletePassed the PMI-ACP exam, with some help from these questions. It is a good additional resource for the test.
ReplyDeleteVery good collection.
ReplyDeleteGood
ReplyDelete
ReplyDeleteThank you for the info. It sounds pretty user friendly. I guess I’ll pick one up for fun. thank u.
Function Point Estimation Training
Hi friend iam providing the safe agile certification of various Courses online training.
ReplyDeleteHi friend iam providing the safe agile training of various online training.
ReplyDeleteThank you!!
ReplyDeleteHi friend iam providing the safe agile certification of various online trainings like PMP,PRINCE2,ACP,PSM,CSM.
ReplyDeleteHi friend iam providing the safe agile certification of various online trainings like PMP,PRINCE2,ACP,PSM,CSM.
ReplyDeleteHi friend iam providing thesafe agile certification training of various certification training.
ReplyDeleteNice, Thanks for sharing .Also you check the best Prince2 Training Mumbai
ReplyDeleteFormally Known As Ulearnsystemssafe agile training in hyderbaf of various certification trainings,Low fee,2 days classroom training.
ReplyDeleteFor latest and updated PMI-ACP certification dumps in PDF format contact us at completeexamcollection@gmail.com. Refer our blog for more details http://completeexamcollection.blogspot.in/
ReplyDeleteExcelent Thanks a lot
ReplyDeleteNice blog, thanks for giving such information. Also you can check the best Agile Project Management Course
ReplyDeleteGood Info,
ReplyDeleteStudy of PMI PMI-ACP exam is not easy without having dumps. You can get PMI-ACP dumps from Dumps4Donwlaod.com this is the finest source for exam study material. They can provide you latest and actual exam questions with verified answers.
Nice article Jan on how to prepare for Learn Acp Certification. I just want to add a few more points like taking mock tests pertaining to each knowledge area and full length mock tests also form key elements behind cracking the Acp Certification successfully. I've recently passed Learn Six Sigma Master Black Belt exam. I took Learn Acp Certification .The training helped me clearing the exam in first attempt without any hassles.
ReplyDeleteAcp Certification Hyderabad
Abur: Thanks so much for sharing this test and answers with us.. It is a lot effort and time from you. Many you coud do a many test and charge for those.
ReplyDeleteAgain, thanks a lot
Many questions I didn´t know the answer, this means that I need study more.
We have been giving amazing examination guide and readiness material to the majority of our clients for quite a while now. Our dedicated specialists are working enthusiastically to give excellent test guide and concentrate material for the clients who need to pass affirmation tests in a solitary endeavor.
ReplyDeleteCertsmarket
Awesome,
ReplyDeleteThank you so much for sharing such an awesome blog...
remote resource
Well article, interesting to read…
ReplyDeleteThanks for sharing the useful information
android development certification
This comment has been removed by the author.
ReplyDeleteThere are free 50 ACP Sample questions here http://www.prozenics.com/Acp-QAs.html
ReplyDeleteI had amazing experience at www.realexamcollection.com because the material that was provided to me was according to my requirement. I didn’t need to go to any other place for preparation and found all what I need at one place. Questions and answers have been presented in very concise form so I learnt every concept with little effort. All what I had to do was to focus on the provided material. After choosing this material for my preparation everything became easier for me. It was not easy to pass this exam without such help so I am thankful for this sincere help and support. PMI PMI-ACP Dumps PDF
ReplyDeletePassing the AI-100 exam is no more difficult, with latest AI-100 dumps pdf anyone can easily pass the AI-100 exam on the first attempt! The best thing is 100% success rate & money back assurance.
ReplyDeletehttps://www.realdumpspdf.com/exam/pmi-acp-dumps-pdf/
Note:- New Questions has been added to the AI-100 PDF.
Get the complete AI-100 Question Answers PDF & Start prepartion:- AI-100 Dumps 2019
Product Features:
1) 100% Success Rate
2) Money Back Assurance
3) Up-to-date Questions
4) Instant Download
5) Free Updates for 3 months
I was confused about the selection of a suitable guide for the preparation of PMI Agile Certified Practitioner (PMI-ACP) Exam. I could not find any better than PMI-ACP Dumps. If I appear in any further IT exam I will definitely download material from Realexamdumps.com. I suggest to all of you to take PMI-ACP Dumps PDF.
ReplyDeleteI would admire the miraculous quality of information which was conferring to the exam of PMI Agile Certified Practitioner. PMI-ACP Dump is efficient and affective source of knowledge. I’ll continue using materials from Dumps4download and will be referring to others.
ReplyDeleteWhen I was told about PMI-ACP dumps, first I downloaded free demo questions from Real exam dumps that gave me an opportunity to look into the material. All the information was authentic and the pattern of PMI-ACP questions and answer.was fully valid. I thank for this guide and appreciate such services.
ReplyDeleteI was able to do rapid preparation with PMI-ACP questions and answers that saved my time and unnecessary efforts. I work through the course and secure grand position with high grades. I think Exam4Help deserves thanks for boosting the career of so many IT students. I am feeling great after passing my exam with PMI-ACP dumps.
ReplyDeleteQuestion: During which project management phase are the product stories delivered? : Correct Answer is Explorer
ReplyDeleteReally impressed! Everything is very open and very clear clarification of issues. It contains truly facts. Your website is very valuable. Thanks for sharing. Digital marketing in pune
ReplyDeleteI was downloaded Acams CAMS dumps PDF in panic because I was not prepared and the time for the commencement of exam was not much. I did this on the suggestion of a friend but I checked the quality through free demo questions too. I am thankful to Dumpspass4sure.com for allowing this quality check. I simply prepared all the questions and answers that were carefully selected by the experts and put in this material and passed my exam with good grades. I am very happy for the right selection of Acams CAMS dumps at the right time. I am so satisfied with these services that I will use the same learning platform if I go for any further IT exam.
ReplyDeleteGood one!!!!! Correct answer for: During which project management phase are the product stories delivered? - Explore (not Speculate). I found the questions and explanations very useful. Thank you team!!!
ReplyDeleteAlthough Cisco is not an easy task to pass but I am happy to ace it by the first attempt. I can’t stop myself from appreciating the work at Dumpspass4sure. Experts have done excellent job. Pass4sure Cisco Dumps have been presented so comprehensively that I got all the concepts by the first read. They have reduced candidates’ efforts by sharing their experience in this form of service. Congratulations to everyone who used Pass4sure Cisco Question and answers like me.
ReplyDeleteI think EXAM4LEAD.COM deserves compliments and appreciation for all the useful work. FREE PMI-ACP DUMPS has been formed out of the honest and sincere work by the experts. I never thought PMI-ACP exam as easy as I took it after preparing from this concise guide. All the syllabus topics were dealt carefully by being relevant. It was not hard to infer the main idea of each topic. Without any difficulty I successfully solved all the questions. It was only through PMI PMI-ACP DUMPS 2020 updated that I got my target score. Very pragmatic approach has been followed while writing this guide book. I am thankful to experts for all the efforts they made for the preparation of this material.
ReplyDeleteDownload Full Exam & Pass 100% Success Guaranteed:
PMI-200
PMI-Agile Certified Practitioner (PMI-ACP)
PMI-ACP
PMI Agile Certified Practitioner
https://www.exam4lead.com/pmi-acp-certification.html
Passing the PMI Agile Certified Practitioner is step toward IT Certification. You must have to pass your pmi-acp exam, so we friendly advice you to learn pmi-acp dumps pdf by us. Realdumpspdf fulfill your pmi-acp exam study material requirments and make 100% authentic pmi-acp exam dumps with actual pmi-acp exam question. And also valid pmi-acp exam practice question to make your preparation effective.
ReplyDeleteFor More Details: https://www.realdumpspdf.com/exam/pmi-acp-dumps-pdf/
You also found these hidden benefits:
Instant Download
Free 90 days updates
100% Passing Guarantee
Updated Study Material
Actual Exam Question
Easy to learn and understand
PMI-ACP has won the trust of so many students by providing the material that fits for everyone with any type of background knowledge. My suggestions are to use this material for any type of IT exam. I could not have passed this exam if I could not find
ReplyDeletePMI-ACP at the right time. I will say thanks to examforsure for fulfilling the guarantee
There was nothing puzzling in PMI-ACP questions and answers. After checking the quality from demo questions, I downloaded the actual PDF file at very cheap price. I cannot express my excitement in words after getting guaranteed success in PMI-ACP and all this happened only with PMI-ACP dumps.
ReplyDeleteIf you are in search of authentic study guide then you should visit DUMPSSURE.COM where you can download PMI-ACP dumps. This has been perfectly designed by qualified experts who are working to make a difference in the knowledge and results of IT students. The experts have an understanding of how the exam are conducted and what are the merits that are used to test candidates. With the use of all their knowledge about the field they have covered full syllabus in the form of Real PMI-ACP questions and answers. Not only this, but they have also developed Online Practice Test that will help you improve your understanding by improving your knowledge. The more you practice the better and desired consequences you will have. PMI-ACP pdf dumps guide is stamped with money back guarantee that assures you of your success and in case of failure you money will be returned. Download demo questions right now for trial and go for your success.
ReplyDeleteActual Exam Dumps Questions Answers
Accurate and valid exam dumps for which are verified by our professionals. Download the lastest exam question answer for from Dumpsadviser.
ReplyDeleteDumpsFactory proved to be a great help for me and nothing hurt me while seeking help from the qualified experts. PMI ACP Dumps played a vital role in my preparation and I was guaranteed to pass my IT exam with this study material. My need for an authentic and valid study material was fulfilled with PMI ACP Dumps. My recommendation for recommendation for everyone is the same guide. We are providing 10% discount, If you are interested then visit our site.
ReplyDeleteGet expert PMP Exam Project Management Professional (New Version) Question & Answer Dumps PDF Online. We Provide latest IT Certification Exams PDF for preparation Study Guide Test Practice for Success in exams. This is an online education portal
ReplyDeleteI passed my PMI PMI-ACP earlier this morning. You know what? I just use PMI PMI-ACP dumps from ExamforSure site, no other books at all! It is really helpful if you do not get much time to prepare your PMI exam. You should have a try. It won't let you down. Why do you want to take roundabout ways if there is a shortcut? Trust me or not. Good luck to you all.
ReplyDeletehttps://www.examforsure.com/pmi/pmi-acp-exam-dumps.html
My hearty thanks are for DumpsSure.com and all the people working for it. I downloaded Real PMI ACP dumps pdf from here which gave me an astute understanding of my discipline with all the technical required knowledge. I was guaranteed to pass my IT exam with PMI ACP questions and answers by the first attempt so expectedly and confidently I passed it. DUMPSSURE
ReplyDeleteIt was my dream to pass PMI PMI-ACP exam but I could never gather courage or get a suitable study material. Finally a friend suggested me to download PMI PMI-ACP dumps PDF from DumpsForSure. I am thankful to the experts who carved it very smartly which helped me realize my dream. I am very happy for my incredible success with PMI PMI-ACP dumps and I suggest the same for everyone.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteRecently, i sat for the exam and managed to pass. I have detailed my experiences here
ReplyDeletePrepare with Actual Exam Questions for Guaranteed Success
ReplyDeleteGet The Best Deal Of 2021 January 40% Discount On
ReplyDeleteI could not have done so astute preparation without PMI-ACP dumps pdf questions material as it gave me the most authentic information in the most concise form. I downloaded PMI-ACP dumps easily from Passexam4sure and started my preparation without any delay.
This comment has been removed by the author.
ReplyDeleteI prepared for my IT exam from PMI-ACP dumps and I think there is no study material of it match. I didn’t see any material of this value and I am thankful to everyone who has been the part of its creation. PMI-ACP dumps material is the most reliable material.
ReplyDeleteI had an amazing experience with RealDumpsCollection which brought me great success in my IT exam. PMI-ACP dumps was really helpful for covering all the syllabus contents in very short period of time. It was because of the handy format of this material which saved me time for practice on online practice test. The experts were very cooperative and showed a good disposition so I will suggest PMI-ACP dumps for everyone.
ReplyDeletePassed this exam an hour ago, no hands on experience with using PMI PMP exam from using the free trial to practice for the test.
ReplyDeleteI used: https://www.dumpsfactory.com/pmi/pmp-dumps.html
I really liked your blog post.Much thanks again.
ReplyDeletepega online training
Best Pega Online Training
learn pega online
This information is really awesome thanks for sharing most valuable information.
ReplyDeleteworkday integration course india
workday online integration course
workday online integration course in india
Nice blog!! keep up the great work. You can also check this Similar site for PMP
ReplyDeletehttps://www.29chat.com/read-blog/288_how-i-success-in-adobe-ad0-e117-exam-with-adobe-ad0-e117-practice-exam-questions.html
ReplyDeleteBuy iPad Pro 11 inch 2nd generation case with pencil holder. Zugucase has an iPad pro 2nd generation case with protective functionality in an affordable range
ReplyDeleteipad pro 12.9 case
ipad pro 11 inch case
iPad Air 10.9 Case (4th Gen) 2020
ipad pro 11 inch 2nd generation case
ipad 10.2 case
ipad mini case
ipad pro 12.9 3rd gen case
ipad pro 11 case
ipad 9.7 case
ipad pro 10.5 case
https://www.lily.fi/blogit/examcerts/nse7_efw-6-4-fortinet-nse-7-enterprise-firewall-6-4/
ReplyDeleteRealdumpspedia.com provides the excellent PMI-ACP practice exam questions for the IPMI Agile Certified PractitionerI am preparing for. Additionally, I used their online dumps which was the best user experience. I actually appreciate their excellent service.
ReplyDeletehttps://www.dumpsowner.com/pmi/pmi-acp-exam-dumps.html
It is so nice blog. I was really satisfied by seeing this blog.
ReplyDeleteworkday training
workday online training
Through this Digital Marketing Training Institute in Panchkula you will become an expert in modules such as SEO, Social Media Marketing, PPC, Analytics, Content, Mobile, and Email Marketing. Our Social Media Marketing and PPC courses in Panchkula have trained end number of students. Work on real-world projects, learn the latest tools, and attend masterclasses led by the Google and Facebook certified team.
ReplyDelete- Get hands-on training on live projects!
- Upgrade your resume
- Get prepared for your dream job.
- 120+ hours of high-quality training.
- 10+ live projects.
- 25+ digital marketing tools and platforms.
Certified Digital Marketing course in Panchkula
ReplyDeleteHer is a Nice & Informative Blog ! We offer welcome to yorkie puppies near me. Check it out!...
ReplyDeleteteacup yorkies for sale
yorkshire terriers for sale
yorkie for sale near me
chihuahua puppy for sale chihuahua puppies for sale
yorkies for sale
ReplyDeleteyorkie puppy for sale near me
yorkie for sale near me
yorkie poo for sale
yorkie for sale
Nice & Informative Blog
ReplyDeleteSalesforce CPQ Online Training Hyderabad
Salesforce CPQ Online Training India
I would not be able to pass my PMI Agile exam without a suitable study material like PMI-ACP. It is only because of this guide that I covered my syllabus within a short period of time. This worthy material makes the experts praiseworthy who designed this helping guide. If I go for any further certification in future my definite selection will be PMI-ACP.
ReplyDeleteFor More Info Visit: https://www.dumpspool.com/pmi/pmi-acp-dumps.html
Amazing post. Informative and knowledgeable content. Keep sharing more stuff like this. Thank you.
ReplyDeleteAI Patasala Data Science Courses in Hyderabad
For a limited time, get any exam PDF file in $30. You get REAL PMI questions and REAL answers to all of the hottest certification exams.
ReplyDeleteAchieve a 100% Pass Rate on over 4000 Exams, prepare and quickly pass the tough IT certification exams.
Unlimited access to IT training Exams and Certifications in PDF format.
Original Questions and Verified Answers for Certification Exams.
Instant Access to all 4000+ of our practice PDF downloads.
Get Fully 100% Updated Dumps Questions: http://www.dumpssolutions.com
This comment has been removed by the author.
ReplyDeleteSeveral questions emerged in my mind before buying their PMI PMI-ACP Dumps
ReplyDelete. All my questions were answered and I really appreciate their immediate support and strong customer support with experience. Keep up this good job.
This was really one of my favorite website. Please keep on posting. Digital Marketing Classes In Pune
ReplyDeleteخرید نهال بادام
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteMany thanks for sharing such kind of info. It is actually not easy to meet the difficulties to Pass your PMP Exam, but if you have valid study material like DumpsToday PMI Exam Dumps. No doubt will pending to be successful.
ReplyDeleteHence its only need to get an authentic study material to prepare any of your exam, than nobody can stop you to be successful in your field..
For More Details:-
https://dumpstoday.com/
mmorpg oyunlar
ReplyDeleteINSTAGRAM TAKÄ°PCÄ° SATÄ°N AL
TÄ°KTOK JETON HÄ°LESÄ°
tiktok jeton hilesi
antalya saç ekimi
ınstagram takipci satin al
İnstagram Takipçi Satın Al
MT2 PVP SERVERLAR
instagram takipçi satın al
My focus was only on PMI-ACP dumps while preparing for my final IT exam. I didn’t consult any other source because I was given handsome knowledge about each topic in this concise guide book. I memorized questions and answers in PMI-ACP Dumps 2022 and easily aced my certification.
ReplyDeleteFon Perde Modelleri
ReplyDeleteMobil onay
Türk telekom mobil ödeme bozdurma
nft nasıl alınır
ankara evden eve nakliyat
trafik sigortası
DEDEKTÖR
Kurma Websitesi
aşk kitapları
Smm Panel
ReplyDeleteSMM PANEL
iş ilanları
İNSTAGRAM TAKİPÇİ SATIN AL
HIRDAVAT
Beyazesyateknikservisi.com.tr
servis
tiktok jeton hilesi
Thanks for providing the valuable information's, this is ver much helpful for the students. Also refer Digital marketing courses in Delhi for details about Online Digital marketing courses.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteGreat Questionnaire!
ReplyDeleteFinancial modeling course
uc satın al
ReplyDeleteyurtdışı kargo
en son çıkan perde modelleri
en son çıkan perde modelleri
özel ambulans
minecraft premium
nft nasıl alınır
lisans satın al
Very impressive post
ReplyDeletecheckout
Thanks for sharing this informational article.
ReplyDeleteCheck out-
Digital Marketing Courses in Delhi
Great questionnaire.
ReplyDeleteBest Digital Marketing Institutes in India
Thank you for your post. Check out Digital Marketing Classes in Pune.
ReplyDeleteGreat content. Visit-Digital marketing courses in Greece
ReplyDeleteThank you for sharing this informational post. Very helpful!
ReplyDeleteIf you are interested in learning digital marketing, here is a complete list of the best online digital marketing courses with certifications. In this article, you will learn about digital marketing and its different strategies, the need for doing digital marketing, the scope of digital marketing, career opportunities after doing online digital marketing, and many more.
Visit-
Online Digital Marketing Courses
Hey great, I really delighted to find this useful informative blog to prepare PMP, which is the most valuable professional skill to earn and to elevate carrier. Thanks for sharing to get the glimpse of the exam. If anyone wants to learn Digital Marketing, Please join the highly demanded and most sought skill by the professionals in all streams due to the remarkable growth predicted by international survey agencies. So join today. Find out more detail at
ReplyDeleteDigital marketing courses in france
This comment has been removed by the author.
ReplyDeleteThis is a very informational blog. to know about digital marketing courses please visit. Digital marketing courses in Ahmedabad
ReplyDeletebest digital marketing institute in pune
ReplyDeleteVisit Windreams
What You Will Learn?
seoBecome a digital marketing specialist by windreams informatives.Become a digital marketing specialist by
SEO (Search Engine Optimization.)
SEMBecome a digital marketing specialist by
SEM (Search Engine Marketing.)
social media marketingBecome a digital marketing specialist by
Social Media Marketing.
emaliBecome a digital marketing specialist by
Email Marketing.
Become a digital marketing specialist by
Content Marketing.
annnliyBecome a digital marketing specialist by windreams informatives.Become a digital marketing specialist by
Analytics.
graphic designBecome a digital marketing specialist by windreams informatives.Become a digital marketing specialist by
Graphic Design
Become a digital marketing specialist by
Mobile Marketing
Our Facilities?
Offline / Online Class
Duration 3 Month Only Fri / Sat / Sun
100% Job Assistance
25+ Topics
Google Certification
Scholarship Program
Wings For Dreams is a social service organization in Pune. Supporting for scholarship to youngsters which are actual want to learn digital marketing and become a financially independent. So the scholarship amount is 20,000/- , it is very big support for youngsters.
Course Fee : 25,000/- (+18% GST)
Scholarship : 20,000/-
Final Fee : 5000/- (+18% GST)
If you refer this course to your friends then you will get 200/- cashback per student.
Informative post, thanks for sharing and keep updating. Content Writing Course in Bangalore
ReplyDeleteExam Dumps To get in advance to your profession and stand satisfied with the opposition, hold in thoughts incomes Exam Dumps Certifications that’ll validate your Exam Dumps competencies and assist you advantage a expert advantage. Beyond the character, having a Exam Dumps Cloud Skill Training & Certification benefits your organisation too.
ReplyDelete
ReplyDeleteThank you for sharing PMI-ACP exam question and answers. It's very helpful for everyone.
If you are interested in building a medical career but are struggling to clear medical entrance exams, Wisdom Academy is the right place to begin. It is one of Mumbai's best NEET coaching institutes for students preparing for medical and other competitive-level entrance examinations. It offers comprehensive learning resources, advanced study apparatus, doubt-clearing sessions, regular tests, expert counseling, and much more. Equipped with highly qualified NEET Home Tutors, Wisdom Academy is one such institute that provides correct guidance that enables you to focus on your goal. Enroll Now!
NEET Coaching in Mumbai
This comment has been removed by the author.
ReplyDeleteI would love to thank you for this blog as it helped my brother in his ACP exam. The questions and choice of answers were helpful. I would also like to share a blog on the Search Engine Marketing which would be helpful to many. Visit -
ReplyDeleteSearch Engine Marketing
I tried tk answer some question but j think i am zero in it. But nice blog.. Keep updating us. Also can have a look on Digital Marketing Courses in Abu Dhabi
ReplyDeleteGreat article. thank you for sharing
ReplyDeleteIf anyone is keen on learning digital marketing. Here is one of the best courses offered by iimskills.
Do visit - Digital Marketing Courses in Kuwait
Good effort you put to give some questions and answer about PMI ACP. Keep it up. Please also Check out the Digital Marketing Courses in Delhi that will help you to upskill and to boost your website. Digital Marketing Courses in Delhi
ReplyDeleteGood information, well written. Financial Modeling Course in Delhi
ReplyDeleteThank you for sharing information.
ReplyDeleteDigital marketing courses in Singapore
I went through your article and not only I liked it but also found it helpful. Digital Marketing courses in Bahamas
ReplyDeleteI loved the quality of information you have provided and I must say you have noted down the points very precisely, keep posting more.
ReplyDeleteVisit- Best Content Writing Courses in India
Hi, knowledgeable and useful blog. The quality of content mentioned is good. This will surely help many of the readers. Thank you.
ReplyDeleteDigital marketing courses in Ghana
Nice blog. Thanks for sharing.
ReplyDeleteDigital marketing courses in Goa
digital partners digital marketing courses in pune
ReplyDeletehttps://www.digitalpartners.in/
8657482176
Office No 201,2nd floor,Samrudhi Market, Sangarsh chouk, chandan Nagar,pune 14
Wow, I found my most interesting subject since I have participated in it. This PMI is not only helpful professionally but helps in many ways in everyone's daily and social life. This teaches us the art of handling the issues and people around us. Thanks for sharing the sample questions to help the community and participants to go forward. If anyone wants to learn Digital Marketing in Austria, Please join the newly designed curriculum professional course on highly demanded skills required by top corporates globally. For more details, please visit
ReplyDeleteDigital Marketing Courses in Austria
Thank you for sharing this multiple choice questions about PMI ACP. This will help many learners to prepare their exams. Keep writing. We also provide an informational and educational blog about Freelancing. Nowadays, many people want to start a Freelance Career without knowing How and Where to start. People are asking:
ReplyDeleteWhat is Freelancing and How Does it work?
How to Become a Freelancer?
Is working as a Freelancer really a good Career?
What is a Freelancer Job Salary?
Can I live with a Self-Employed Home Loan?
What Kind of Freelancing Jobs are Skills are required?
How to get Freelance projects?
How Do companies hire Freelancers?
In our Blog, you will find a guide with Tips and Steps which will help you to take a good decision. Check it out:
What is Freelancing
Hello Admin!
ReplyDeleteThanks for the post. It was very interesting and meaningful. I really appreciate it! Keep updating stuffs like this. Content Writing Courses in Delhi
Thanks for sharing the question and answers its very helpful. Learn digital marketing from the industry experts visit to know more Digital Marketing Courses in Dehradun
ReplyDeleteThis blog was a pleasure to read Digital marketing courses in Gujarat
ReplyDeleteI just wanted to appreciate the fact that this article has provided useful exam questions. I found it really helpful. Digital Marketing Courses in Faridabad
ReplyDeleteThank you for sharing questions and answers. Helped me a lot.
ReplyDeleteDigital Marketing Courses in Pune
Premium Exam Files, Question and Answers for Microsoft DP-900 are actually exam dumps which help you pass quickly. Don’t get scared of opting for Exam DP-900! It’s now just a piece of cake! Rely on Marks easy DP-900 Questions Answers that can give you first time success with 100% money back guarantee! Thousands of IT professional have already been benefited with the marvelous DP-900 Q&As and have obtained their dream certification.
ReplyDeletehttps://pass2dumps.com/best-exam-dump-sites/
https://examlabsdumps.com/
hi, all the mcqs are very uniquely defined with explanation of answer also.I enjoyed reading your blog. Keep up the good work. Digital marketing courses in Kota
ReplyDeleteGood Outlook! https://advisoruncle.com/data-analytics-scope/
ReplyDeleteCreative Writing Courses in Hyderabad
ReplyDeletedata analytics in Jaipur, a good catch for job and here is the link you can find info. Top 5 Data Analytics Courses in Jaipur.
ReplyDelete120 Question are definitely unique and well explained.It is amazing and wonderful to visit your site. Thanks for sharing this information, this is useful to me.. Digital marketing Courses in Bhutan
ReplyDeleteThe Mcq questions shared here are important and is helpful for jobseekers , share such MCQ more and more.
ReplyDeleteDigital marketing courses in Raipur
Very informative article and good for PMI preparation. I have qualified PMI and I know how precious it is. You are doing a great help those who do not have enough resources to prepare for the competition. If anyone wants to build his carrier in Digital Marketing then you must go through our curriculum which is designed very professionally with cutting edge of the current requirement of the corporates and based on market trends. For more detail Please visit at
ReplyDeleteDigital marketing Courses In UAE
nice set of question answers discussed by you, it s going to help readers like me. Data Analytics Courses In Ahmedabad
ReplyDeleteThese article on PMI-ACP exam dumps question is so helpful to learn something new out of it. Data Analytics Courses in Delhi
ReplyDeleteThank you for posting the sample questions along with its correct answers. it really helping for students like us who are preparing for the PMI-ACP exam. keep up the great work.
ReplyDeleteData Analytics Courses In Kolkata
Great information about \Free PMI-ACP exam dumps 120 Quest, I will Definitely share this information with my friends who are looking to crack an exam related to this topic. Thank you for sharing! Digital Marketing Courses in Australia
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteThis blog provides great option for anyone looking to get certified in PMI-ACP! The exam dumps are very amazing, fabulous and well written. I would definitely recommend this to anyone looking to get their PMI-ACP certification. Digital Marketing Courses in Vancouver
ReplyDeleteHi, thank you for sharing this informative and knowledgeable blog for PMI preparations. This would surely help many students who would not afford to prepare for the same. This will surely help build their confidence.
ReplyDeleteData Analytics Courses In Kochi
This is one of the best resource for someone looking for PMI-ACP exam dumps 120 Quest, This allows them to go through some important and very well known information included in this exam quest. Thanks for sharing it with us! Data Analytics Courses in Gurgaon
ReplyDeleteVery knowledgeable post. Digital marketing courses in Varanasi
ReplyDeleteVery useful information on PMI-ACP exam. Data Analytics Courses in navi Mumbai
ReplyDeleteVery useful questions for those who want to be certified in PMI -ACP course Data Analytics Courses In Bangalore
ReplyDeleteThank you for sharing these multiple-choice questions about PMI ACP. useful article and good for PMI preparation.
ReplyDeleteData Analytics Courses in Kota
Data Analytics is the course where we learn the compilation of various sets of data. In easy language, it is said to collect, store, and analyze the data set for perfect business goals. The top data analytics courses in India here to give you a clear idea of what to expect from training programs on data analysis.
This is a great post! The PMI-ACP exam is definitely a difficult one, and these free dumps are a great resource. Thank you for sharing!
ReplyDeleteKeep up the good work! Data Analytics Courses In Coimbatore
Thanks a lot for uploading PMI - ACP exam quest with us. It is an excellent thought to do this in an article. I highly appreciate the effort you have put into this blog. This article will be handy for newbies. Keep sharing the more valuable article in the future too.
ReplyDeleteDigital marketing courses in Nagpur
Great informative article. This PMI knowledge is awesome and very significant to acquire professionally which is truly very useful for better results and process orientation. Sharing some specimen question to get the idea about PMI is really good. If anyone wants to build his carrier in Digital Marketing then you must go through our curriculum which is designed very professionally with cutting edge of the current requirement of the corporates and based on market trends. For more detail Please visit at
ReplyDeleteDigital marketing Courses In UAE
This is one of the greatest sources for PMI-ACP exam dumps 120 Quest because it enables users to read through some crucial and widely recognized material that is contained in the exam quest. We appreciate you sharing it with us.
ReplyDeleteData Analytics Courses in Ghana
The article is definitely having good set of questions. Useful for PMI-ACP definitely. Globally, the process is fine but it would have been appreciated if the answers were available on a separate page so that one could view the answers afterwards.
ReplyDeleteData Analytics Courses in New Zealand
This article provides excellent information. Many thanks for the PMI - ACP exam search. I appreciate how you explained it. Please post additional blogs about the PMI-ACP in the future. I must mention the effort you have invested in this blog. Good work. Please keep spreading it.
ReplyDeleteCourses after bcom
I appreciate you sharing such great information. The level of detail on your website is impressive. It demonstrates how well you comprehend this subject. I bookmarked your post and will return to read more stuff.
ReplyDeleteData Analytics Courses in Mumbai
Unique and beneficial article. Thanks a lot for PMI - ACP exam quest. The way you have explained it is highly appreciatable. Please upload more PMI-ACP-related blogs because they will be valuable for those who seek them. Please don't stop sharing it. Digital marketing courses in patna
ReplyDeleteFantastic blog! Exceptionally well-written and very educational! These free exam dumps are an excellent resource because the PMI-ACP exam is unquestionably challenging. I appreciate you sharing.
ReplyDeletefinancial modelling course in kenya
hi, i am kiran and all these question with EXPLANATION of PMI-ACP exam are fabulous and well written. thanks for spending time to write all the questions. keep sharing.. Data Analytics Courses In Indore
ReplyDeleteThank you for listing out PMI-ACP exam samples. Its a great for students. It Definity cut lots of time and efforts of students in searching . Keep sharing more useful articles like this.
ReplyDeleteData Analytics Courses In Nagpur
This blog is incredibly well-crafted and incredibly informative. The free exam dumps are an amazing resource since the PMI-ACP exam is certainly difficult. Much thanks for sharing this.
ReplyDeletefinancial modelling course in bangalore
Thanks for sharing the 120 quests of the ACP exam for free. The q&a you have shared is helpful for the students who seek to do a mock and find their level of expertise. Moreover, the explanation for the answer is also very crisp and clear. I appreciate the effort taken by the author for this article. Thanks once again. Keep posting more insightful weblogs in the future. Financial modelling course in Singapore
ReplyDeleteThanks for sharing PMI-ACP exam questions. These are really useful for us. financial modelling course in gurgaon
ReplyDeleteHello Blogger,
ReplyDeleteyou gave a free and self training session here! Thank you for making it happen. I went through it, and I appreciate it. nice work!
Thanks for sharing this valuable post with us. The Q&A of the agile PMI ACP test is what I am looking for. Though many articles share this type of Q&A, they won't explain it, but this blog does. I am pleased to find this post. It gives a sense of confidence before facing an actual exam. Once again, thanks a lot for the blog post. Do continue to post more helpful articles. Data Analytics courses in leeds
ReplyDeleteI have qualified PMI and I know how important it is. You are doing a very great help to those who do not have enough sources to prepare for the competition. Also, if anyone is interested in learning more about Financial modelling course in Jaipur, then I would like to recommend you with this article on: financial modelling course in jaipur
ReplyDeleteIt is a great tutorial actually dear blogger,
ReplyDeletethose are good questions to note. Thanks again. data Analytics courses in thane
I appreciate you providing the free ACP mock questions. The Q&A you provided is beneficial for students who want to upgrade their knowledge in the upcoming exams. Also, the reasoning under every question is concise and easy to understand. I admire the time and effort the author put into this piece. Again, thanks a lot. Continue publishing enlightening posts in the future. Data Analytics courses in Glasgow
ReplyDeleteI have been reading out some of your posts and i can state pretty nice stuff. I will make sure to bookmark your website.
ReplyDeleteBest Digital Marketing Institute In Delhi
I am delighted you are sharing this insightful article with us. What I'm searching for is the agile PMI ACP exam Q&A. While many publications include this kind of Q&A, they don't usually explain it; this blog does. I'm glad I came across this article. It instills confidence before taking the actual exam. Thank you very much for the blog post. Keep publishing more informative stuff. Data Analytics Scope
ReplyDeleteHi blogger,
ReplyDeleteI think the sample question you used in you blog post is great. It is meaningful enough to describe a data. Thank you for sharing it with us all. Data Analytics Course Fee
Hello blogger, this list of PMI Agile certified practitioner Q&A is remarkable, especially the explanations to the multiple choice questions makes it a lot more easier to understand. Thank you for this informatory content.
ReplyDeleteData Analytics Jobs
Very useful mcqs. I am glad to find this post... Data Analyst Interview Questions
ReplyDeleteHi dear blogger,
ReplyDeleteYou have made an interesting blog post. Thank you for sharing your knowledge with us all. I like it Business Analytics courses in Pune
I'm grateful that you shared this helpful post. It will be valuable for the students who want to improve their knowledge for the upcoming exams. The Q&A you supplied is helpful. This mock test boosts their confidence before taking the real one. Moreover, each question's justification is clear and understandable. Thanks for the post. Continue to publish more educational content. Data Analyst Course Syllabus
ReplyDeleteThe article is really helpful in sharing knowledge about PMI ACP related exam questions. If anyone wants to learn Data Analyst Salary In India then kindly join the newly designed curriculum professional course with highly demanded skills. You will be taught in a professional environment with the given practical assignments which you can decide in your specialized stream. Data Analyst Salary In India
ReplyDeleteThe list of questions along with the answers as well as explanation to them can be very beneficial to PMI ACP examinees. Also checkout
ReplyDeleteData Analytics VS Data Science
Hello blogger,
ReplyDeleteIt was great to discover this tutorial. I appreciate the content, it is very informative to me. Thanks for making this post.
Data Analytics Qualifications
These MCQs are quite impressive I very helpful for jobseekers. I really appreciate the blogger upload to this amazing content Best Financial modeling courses in India
ReplyDeleteGreat info.! Your blog post must be very important for the readers out there. Thanks for sharing.
ReplyDeleteCA Coaching in Mumbai
very useful blog for ACP exams. The MCQs mentioned are quite remarkable Best GST Courses in India
ReplyDeleteThese PMI-ACP dump questions are really helpful for one's preparation of examinations and these Mcq question's are too good. Also, if anyone is interested in learning more about Best GST Courses in India, then I would like to recommend you with this article on the Best GST Courses in India – A Detailed Exposition With Live Training. Best GST Courses in India
ReplyDeleteHi blogger,
ReplyDeleteyour article showed an important samples of questions. They are useful ones, thanks for making this. Best Content Writing Courses in India
PMI ACP stands for Project Management Institute's Agile Certified Practitioner and is an industry-recognized certification. It is designed to validate the knowledge and skills needed to successfully work in an agile environment. The PMI ACP certification is based on the Agile Manifesto and the 12 principles of agile development. It covers topics such as iterative and incremental development, self-organization, continuous improvement, and stakeholder collaboration. Candidates must pass an exam to earn the certification, and must complete 21 hours of training and have at least 1500 hours of agile project experience in the two years prior to taking the exam. The PMI ACP certification teaches the skills needed to successfully implement Agile projects and to lead Agile teams.
ReplyDeleteThis is an excellent blog written by you to help PMI-ACP aspirants. You have provided 120 questions with answers which are of great help for the exam preparation. You have organized the blog in a simple way with all the questions divided into different categories. The explanation to the answers is really helpful. Your blog has surely helped many aspirants to understand the concepts better and succeed in the exam. Thank you for taking the effort to write such a great blog. Best Technical Writing Courses in India
ReplyDeleteYou did an amazing job of writing this blog. It is very informative and helpful for those who want to learn about PMI-ACP exam dumps. You provided 120 questions which are an excellent way to practice and prepare for the actual exam. I really appreciate the effort you put into this blog and the fact that you provided it for free. Thank you for taking the time to share your knowledge and expertise. FMVA
ReplyDeleteThis article is very helpful for students and very well explained. Thank you for sharing keep posting like this.
ReplyDeleteBest Tally Courses in India
You have done an amazing job in creating this blog post! It is a great resource for anyone wanting to get certified in PMI-ACP, since it provides 120 free exam questions. The questions in the blog are explained in a clear and concise manner and provide the reader with detailed explanations. I believe that the information provided here will be extremely helpful for the readers to prepare for their PMI-ACP exam. I thank you for taking the time and effort to create this invaluable blog post. Best Technical Writing Courses in India
ReplyDeleteYou have done a wonderful job in writing this blog. It is really helpful in providing free PMI-ACP exam dumps of 120 questions. I am sure that this blog will be extremely useful for those who are preparing for the PMI-ACP exam. The information you have provided is very detailed and comprehensive. You have also included the answers which makes it easier to understand. I really appreciate your effort in writing this blog and providing such valuable information to help others. Thank you. Digital Marketing Courses in Glassglow
ReplyDeleteHi, Really Interesting blog, Thanks for Sharing. Data Analytics Courses on LinkedIn
ReplyDeleteHey Fabulous Article got to learned so much about it. Thankyou for sharing the Article on this subject. “Free PMI-ACP exam dumps 120 Quest ” gives us great deal of information about the subject. Keep producing such great content and keep it up.
ReplyDeleteDigital Marketing Courses in Austria
Thankyou for sharing this information with us.
ReplyDeleteDigital marketing courses in Chesterfield
Thankyou for these Q/As . These are very informative.
ReplyDeleteDigital Marketing Courses In Norwich
Nice post for practice. Thank you for sharing the Q n A.
ReplyDeleteDigital Marketing Courses In Krugersdorp
This is the great content for the PMI-ACP-exams dumps, amazing efforts those explanation going help a lot, clearing all doubts. Keep posting. Best Data analytics courses in India
ReplyDeleteGreat information regarding PMI-ACP exam, Appreciate your efforts. keep sharing.
ReplyDeleteBest Data analytics courses in India
Gosh! I appreciated reading the information you provided; thank you. I like reading what you have to say.
ReplyDeleteDigital Marketing Courses In Tembisa
Hey, this list of questions is very informative. The multiple choice questions along with the answers and justification will be very beneficial to PMI ACP aspirants. Keep sharing such insightful blogs. Best Tally Courses in India
ReplyDeleteThank you for the free PMI ACP exam 120 Quest. It helps the knowledge.
ReplyDeleteDigital Marketing Courses In hobart
Useful for preparations in exams.
ReplyDeleteBest Free online digital marketing courses
Great source of learning. Thankyou for sharing.
ReplyDeleteDigital Marketing Courses In Bahrain
Amazing article buddy. Yes, definitely this is a good post without any doubt. You are doing a great job. I am really inspired by your thoughts. It is really valuable.
ReplyDeleteDigital Marketing Courses In Atlanta
Very helpful article.
ReplyDeleteHow Digital marketing is changing business
It's really an beautiful article,, this blog is very helpful for them who is seeking for PMI-ACP exam.. Kindly share more informative article like this
ReplyDeleteTypes of digital marketing which is ideal
This is a thought-provoking article
ReplyDeleteSocial media marketing ideas