Monday, September 9, 2013

Free PMI-ACP exam dumps 120 Quest

Question: Which of the following BEST describes ROTI?

Options:
A. Measure of product backlogs remaining
B. Measure of quality of features delivered in an iteration
C. Measure of required effort to deliver in an iteration
D. Measure of effectiveness of the retrospective meeting
Explanation : Correct Answer is D. Return on Time Invested (ROTI) is used to measure the effectiveness of the retrospective meetings from the team members' perspective.
Question: Technical debt is the gap between a product's actual cost of change (CoC) and its optimal CoC. Managing technical debt helps ensure reliable delivery today and ready adaptation to tomorrow's customer needs. When can Technical Debt occur?

Options:
A. During Initial Development
B. Ongoing Maintenance
C. During enhancement
D. During all the above mentioned times
Explanation : Correct Answer is D. Technical debt can arise during initial development, ongoing maintenance (keeping a product at its original state), or enhancement (adding functionality).
Question: Which of the following is NOT a characteristic of Agile project manager?

Options:
A. Manages daily tasks of the team members
B. Assumes different leadership styles for different stages of team formation
C. Allows team to self-manage
D. Facilitates collaboration
Explanation : Correct Answer is A. Agile Project Manager does not manage the daily tasks of team members as teams in Agile are self organizing.
Question: For a Retrospective meeting, the seating arrangement should be such that there is enough space for people to move comfortably. Which of the following is a preferable seating arrangement for a retrospective meeting?

Options:
A. Circle or semicircle of chairs
B. Theatre style arrangement
C. Tables arranged in U-shape
D. Meeting Room
Explanation : Correct Answer is A. circle or semicircle of chairs encourages participation because people can see each other. Classroom or theater-style arrangements stifle participation. Staring at the back of someone else’s head isn’t conducive to conversation. Tables can be a physical barrier that becomes a psychological barrier. Avoid rooms with an immovable conference table in the middle. That big ol’ table will inhibit creative collaboration. This isn’t a board meeting, after all. Tables arranged in a U-shape with a big gulf in the middle create distance and make it hard to move around.
Question: If we plan to work in a two-week iterations with thirteen iterations during the project and the team’s velocity will be twenty story points or ideal days per iterations, what will the size of the total project in story points be?

Options:
A. 13
B. 20
C. 260
D. 200
Explanation : Correct Answer is C. The size of the total project will be 13 x 20 = 260 story points
Question: What does acronym DRY stand for?

Options:
A. Don't Repeat Yourself
B. Don't Reject Yourself
C. Do Repeat Yourself
D. None of the above
Explanation : Correct Answer is A. This clever name for a well-known principle comes from Dave Thomas and Andy Hunt. Don’t Repeat Yourself is more than just avoiding cut-and-paste coding. Eliminating duplication decreases the time required to make changes. You need only change one part of the code. It also decreases the risk of introducing a defect by making a necessary change in one place but not in another.
Question: Which of the following technique of Scrum requires that every slice of functionality created by the developers be complete?

Options:
A. Team Collaboration
B. Sashimi
C. Scrum tool
D. Ability
Explanation : Correct Answer is B. Scrum uses the sashimi technique to require that every slice of functionality created by the developers be complete. All of the requirements gathering and analysis, design work, coding, testing, and documentation that constitute a complete product are required to be completed in every Sprint and demonstrated in the Sprint increment of functionality. Sprints are kept short enough that the stakeholders don’t lose interest in the project before the Sprints are completed. And stakeholders can see that they have an opportunity to redirect the project at the start of every Sprint to optimize the value they derive from the project. At the end of every Sprint, stakeholders see new functionality. Models, requirements, and internal artefacts might be of use to the developers, but they are never shown to the stakeholders.
Question: What is MOST true about Participatory Decision Making?

Options:
A. It is a technique that involves all the affected parties
B. It is just a meeting with no outcomes
C. It only involves the customer and the Product Manager
D. It is a technique based on the wishes of the Scrum Master
Explanation : Correct Answer is A. It is a technique that involves all the affected parties
Question: Team 1 has been asked to complete work on Item 10 story and deliver it to Team 2 so that they can initiate work on Item 12 story, which is dependent on completion of Item 10 story. The leader of Team 1 decides to insert a buffer that protects the start date on Item 12 story against delays in the completion of Item 10 story. This buffer is known as,

Options:
A. Feeding Buffer
B. Iteration Buffer
C. Story Buffer
D. Release Buffer
Explanation : Correct Answer is A. The Feeding buffer protects the start date on Item 12 story against delays in the completion of Item 10 story.
Question: Sometimes stories are too small. A good approach for tiny stories, common among Extreme Programming teams, is to combine them into larger stories that represent from about a half-day to several days of work. The combined story is given a name and is then scheduled and worked on just like any other story. Which of the following are NOT examples of small stories?

Options:
A. Bug Reports
B. Bugs
C. User Interface Changes
D. A & C
Explanation : Correct Answer is B. A story that is too small is typically one that the developer says she doesn't want to write down or estimate because doing that may take longer than making the change. Bug reports and user interface changes are common examples of stories that are often too small.
Question: Which of the following BEST describes Task Board?

Options:
A. The task board is always a white board
B. It is a great tool to show the project trend
C. It serves the dual purpose of giving the team a convenient mechanism for organizing their work and a way of seeing at a glance how much work is left.
D. Task Boards plot the Velocity
Explanation : Correct Answer is C. Task Board serves the dual purpose of giving the team a convenient mechanism for organizing their work and a way of seeing at a glance how much work is left. It may not always be a white board, it can be a cork board or cardboard too.
Question: Wideband Delphi is a repeatable process that can be used :

Options:
A. To generate estimate
B. To create a story
C. For implementation purpose
D. To motivate the team
Explanation : Correct Answer is A. Wideband Delphi is a technique that is used to generate estimation.
Question: Which of the following is NOT an attribute of a Good Story?

Options:
A. Testable
B. Large
C. Independent
D. Negotiable
Explanation : Correct Answer is B. A good story has six attributes - Independent, Negotiable, Valuable to users or customers, Estimatable, Small and Testable
Question: A story estimated at one story point actually took two days to complete. How much does it contribute to velocity when calculated at the end of the iteration?

Options:
A. One Point
B. Three Points
C. Two Points
D. Cannot be calculated
Explanation : Correct Answer is A.
Question: In the Agile Team Stages of Shu Ha Ri, what does 'Ha' stand for?

Options:
A. Break the rule
B. Follow the rule
C. Be the rule
D. None of the above
Explanation : Correct Answer is A. One good model for mastering anything (if that’s possible) comes from martial arts. A martial arts student progresses through three stages of proficiency called Shu Ha Ri. Shu: Follow the rule. Ha: Break the rule. Ri: Be the rule.
Question: What does 'R' stand for in ARCS, a criteria for evaluating Instructional designs by J.M. Keller?

Options:
A. Relevance
B. Repeatable
C. Recording
D. Right
Explanation : Correct Answer is A. J. M. Keller, an expert in motivation and learning, developed criteria for evaluating instructional designs. The criteria are Attention, Relevance, Confidence/Competence, Satisfaction—ARCS for short. Choose activities that help people stay engaged so they don’t drift off (Attention) and that are relevant to the goal (Relevance). You want activities that people can accomplish successfully (Confident/Competence). Finally, make sure activities fit into the overall design so people think the retrospective is a good use of their time (Satisfaction).
Question: As per the Kano Model of customer satisfaction, which features are MOST important for the product to be successful?

Options:
A. Exciters
B. Linear Features
C. Delighters
D. Threshold
Explanation : Correct Answer is D. Threshold features are those that must be present in the product for it to be successful. They are often referred to as must-have features.
Question: Which of the following defines the splitting of a story or a feature into smaller, easier-to-estimate pieces?

Options:
A. Decomposition
B. Disaggregation
C. Theme
D. Epic
Explanation : Correct Answer is B. Disaggregation refers to splitting a story or feature into smaller, easier-to-estimate pieces. If most of the user stories to be included in a project are in the range of 2-5 days to develop, it will be very difficult to estimate a single story that may be 100 days.
Question: Which of the following is NOT true about Retrospective?

Options:
A. It helps decide how team will work in the future
B. It helps to reflect and learn from the past
C. It allows the team to own and drive their development process
D. It decides who will work on the next project
Explanation : Correct Answer is D. Retrospective is a meeting where a team looks back on a past period of work so that they can learn from their experience and apply this learning to future projects.
Question: Affinity Estimating is a technique many teams use to quickly and easily estimate a large number of user stories. What should be the minimum size for the items in the Product Backlog?

Options:
A. 20
B. 40
C. 8
D. 5
Explanation : Correct Answer is A. •The Affinity Estimating exercise is best conducted on Product Backlogs larger than 20 items. It is best when you have at least 40 items which allows for groupings to easily become apparent.
Question: Of the listed options, which BEST describes User Stories?

Options:
A. Support tools for analysis
B. IEEE 830
C. Use Cases
D. Interaction Design Scenarios
Explanation : Correct Answer is A
Question: Which of the following is NOT a principle from the Agile Manifesto?

Options:
A. Our highest priority is to satisfy the customer through early and continuous delivery of valuable software.
B. Business people and developers must work together daily throughout the project.
C. Continuous attention to technical excellence and good design does not enhance agility.
D. Working software is the primary measure of progress.
Explanation : Correct Answer is C. Continuous attention to technical excellence and good design enhances agility.
Question: Which of the following will NOT assist in Critical Problem solving during the project?

Options:
A. Ask probing questions
B. Use Active Listening
C. Use Reflective Listening
D. Injecting ideas
Explanation : Correct Answer is D. During critical problem solving, you can ask probing questions, use active and reflective listening, Lead to an answer but one should avoid injecting their own ideas.
Question: What is the successful response option at Conflict Level 1 : Problem to Solve ?

Options:
A. Collaboration
B. Consensus
C. Safety
D. A&B
Explanation : Correct Answer is D. Successful response options at Level 1 are, Collaboration- Seeking a win-win situation. Consensus- Learning where every team member’s head is with regard to the issue and, in time, arriving at a decision everyone can back.
Question: John and Joseph are working in the same room. John is programming and Joseph is having some discussion with Kim. John gets to hear their conversation and gets enough information to know that Joseph has talked about some idea with Kim. What kind of communication is this referred to as?

Options:
A. Push Communication
B. Osmotic Communication
C. Pull Communication
D. Active Listening
Explanation : Correct Answer is B. While writing, reading, typing, or talking, we pick up traces of the ongoing sounds around us, using some background listening mode, even though we are not consciously paying attention. If someone says something interesting, we may perk up and join the conversation. Otherwise, the sound goes through some background processing, either just above or just below our conscious level. In some cases, we register enough about the conversation to be able to develop what we need directly from memory. Otherwise, we may recall a phrase that was spoken, or perhaps only that a particular person was discussing a particular topic. In any case, we can ask about it. This taking in information without directly paying attention to it is like the process of osmosis, in which one substance seeps from one system, through a separator, into another. Osmotic communication further lowers the cost of idea tran sfer.
Question: At a Retrospective meeting, a few issues are highlighted by the team. Who is responsible for solving these issues?

Options:
A. The Scrum Master
B. Product Owner
C. Stakeholders
D. Team
Explanation : Correct Answer is D. Agile teams are self organizing and can find solutions to their problems with ease.
Your Answer :  No option selected.
Question: A methodology that is based on solutions or sequences of steps that is known to work for the discipline is known as,

Options:
A. Normative
B. Rational
C. Heuristic
D. Participative
Explanation : Correct Answer is A. Normative methodologies are based on solutions or sequences of steps known to work for the discipline. Electrical and other building codes in house wiring are examples. In software development, one would include state diagram verification in this category.
Question: Having problems does not indicate a problem in itself, so welcome problems because they bring with them the chance for the team to overcome, grow, and become stronger together." As an Agile Coach, which are the multiple perspectives to analyse to detect the symptoms for the problem?

Options:
A. Process Level
B. Quality and Performance Level
C. Team dynamics dimension
D. All of the above
Explanation : Correct Answer is D. The multiple perspectives to analyze are , ? The process level: How are we doing with agile? ? The quality and performance angle: How can the team produce better? ? The team dynamics dimension: How can the team become a better team?
Question: According to DeMarco, Fragmented knowledge workers may look busy but a lot of their business is just thrashing. The minimum cost penalty is :

Options:
A. 15%
B. 10%
C. 5%
D. 25%
Explanation : Correct Answer is A. The minimum cost penalty is 15%.
Question: When can a plan be changed in Agile Management?

Options:
A. At the end of the Iteration
B. When we have learned something new
C. At the Daily Meeting
D. You cannot change once the plan is prepared
Explanation : Correct Answer is B. In Agile, you can change the plan when something new is learned or when it is known that a mistake is to be avoided
Question: What is the normal time estimate for a research story?

Options:
A. 1 day
B. 1 hour
C. Half an hour
D. 1 iteration
Explanation : Correct Answer is A.
Question: What do you mean by Throughput?

Options:
A. Is the amount of production over time
B. Is the number of features the team can develop in a particular amount of time.
C. Is the number of features released during a Release
D. Is the number of defects rectified during a Release
Explanation : Correct Answer is B. Throughput is the number of features the team can develop in a particular amount of time.
Question: Which of the following documents defines the functional and non-functional requirements that the system should meet to deliver the vision, prioritized and estimated?

Options:
A. Prioritized Sprint
B. Vision Box
C. Product Backlog
D. Sprint Review Meet
Explanation : Correct Answer is C. The Product Backlog defines the functional and nonfunctional requirements that the system should meet to deliver the vision, prioritized and estimated.
Question: Which of the following charts shows the total number of story points completed through the end of each iteration?

Options:
A. Iteration burndown chart
B. Cumulative story point burndown chart
C. Daily Burndown chart
D. Burn up chart
Explanation : Correct Answer is B. A cumulative story point chart is useful because it shows the total number of story points completed through the end of each iteration.
Question: Agile Teams use Planning Poker for estimation. Which of the following is NOT true about Planning Poker?

Options:
A. It combines expert opinion, analogy, and disaggregation into an enjoyable approach to estimating that results in quick but reliable estimates.
B. Participants include all of the developers on the team
C. The team for Planning Poker should not exceed more than 10 participants
D. The highest estimate is considered the final estimate
Explanation : Correct Answer is D. If estimates differ, the high and low estimators explain their estimates.

Options:
A. Displaying Work Breakdown
B. Displaying Project Status
C. Automated Build Report
D. Iteration Planning
Explanation : Correct Answer is D. Iteration Planning.
Question: The retrospective meeting on previous iteration should last not more than,

Options:
A. 30 minutes
B. 60 minutes
C. 10 minutes
D. 5 minutes
Explanation : Correct Answer is B. The retrospective meeting on previous iteration should be maximum of one hour.
Question: To detect problems at the process level, The team uses a questionnaire that lists required elements and qualities that are the basic ingredients of agile. From this, we consider anew whether the team truly adheres to their agile process. This questionnaire is referred to as,

Options:
A. Health Check
B. Form
C. Questionnaire
D. Checklist
Explanation : Correct Answer is A.
Question: Spike solutions are small standalone programs that demonstrate what you’ve learned. Which of the following types of spike will you use if you need to test an approach to your production code?

Options:
A. Development Spike
B. Design Spike
C. Scheduling Spikes
D. Iteration Spikes
Explanation : Correct Answer is B. If you need to test an approach to your production code, Perhaps you want to see how a design possibility will work in practice, or you need to see how a persistence framework will work on your production code.
V
Question: DSDM uses MoSCoW technique to create the prioritized requirements list. In MoSCoW technique, 'M' stands for :

Options:
A. Medium
B. Must Have
C. Must Not Have
D. Minimum Marketable Features
Explanation : Correct Answer is B. DSDM popularized the MoSCoW prioritisation scheme, deriving its name from the first letters of its labels of “Must…”, “Should…”, “Could…”, “Would like to have, but not this time.” Under MoSCoW, we have some easier-to-defend categories. “Must-have” requirements or features are fundamental to the system; without them, the system does not work or has no value. “Should have’s” are important--by definition, we should have them for the system to work correctly; if they are not there, then the work-around will likely be costly or cumbersome. “Could have’s” are useful net additions that add tangible value, and “Would like’s” are the “also-ran” requests that are duly noted--but unlikely to make the cut.
Question: Which are the three coach styles?

Options:
A. Teaching, Coaching and Advising
B. Coaching, Mentoring and Advising
C. Coaching, Informator, Advising
D. Mentoring, Teaching and Advising
Explanation : Correct Answer is A. The three coach styles are Teaching, Coaching, and Advising.
Question: One of your stakeholder is interested in viewing the project progress but he is not interested in details. Which of the following report can you share with this stakeholder?

Options:
A. Weekly demo
B. Vision Statement
C. Release plan
D. Burn up chart
Explanation : Correct Answer is D. Burn-up chart is an excellent way to get a bird’s-eye view of the project. It shows progress and predicts a completion date. Most teams produce a burn-up chart when they update their release plan.
Question: Who specifies Acceptance Tests in an Agile Project?

Options:
A. Customer
B. Programmer
C. Developer
D. Product Manager
Explanation : Correct Answer is A. Because the software is being written to fulfil a vision held by the customer, the acceptance tests need to be specified by the customer. The customer can work with a programmer or tester to actually create the tests, but minimally the customer needs to specify the tests that will be used to know when a story has been correctly developed
Question: One of your stakeholder wants more detail than the vision statement provides, but not the overwhelming detail of the release and iteration plans. Which of the following progress report will you share with this stakeholder?

Options:
A. Roadmap
B. Status email
C. Iteration plan
D. Productivity chart
Explanation : Correct Answer is A. Some stakeholders may want more detail than the vision statement provides, but not the overwhelming detail of the release and iteration plans. For these stakeholders, consider maintaining a document or slide deck that summarizes planned releases and the significant features in each one.
Question: Which of the following defines Elapsed Time?

Options:
A. Is the same as Ideal Time
B. Is the amount of time that passes on a clock or perhaps a calendar
C. Is the amount of time that something takes when stripped of all peripheral activities
D. Is the amount of time the team spent on the iteration
Explanation : Correct Answer is B. Elapsed Time Is the amount of time that passes on a clock or perhaps a calendar.
Question: When a team member approaches the Coach with a complaint about another team member, what conflict resolution technique should the Coach use?

Options:
A. Two-step intervention path
B. Face to Face
C. Three-step intervention path
D. Confronting
Explanation : Correct Answer is C.
Question: Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to cost 56%, what is the priority of this feature using relative weighting?

Options:
A. 0.34
B. 0.61
C. 1.64
D. 0.625
Explanation : Correct Answer is B. The priority of the feature is determined by dividing the priority %by the cost %. Hence the answer = (12/35)/(0.56) = 0.61.
Question: How is the Retrospective meeting BEST conducted?

Options:
A. Set the stage, Gather data, Generate Insights, Decide on what to do, Close the Retrospective
B. Gather data, Generate Insights, Decide on what to do, Set the stage, Close the Retrospective
C. Set the stage, Gather data, Decide on what to do, Generate Insights, Close the Retrospective
D. Decide on what to do, Set the stage, Gather data, Generate Insights, Close the Retrospective
Explanation : Correct Answer is A. The correct sequence is Set the stage, Gather data, Generate Insights, Decide on what to do, Close the Retrospective
50 )Question: Which of the following BEST describes error-feedback ratio?

Options:
A. Time spend to fix the hard bugs
B. Number of defects corrected in a specific time
C. Number of errors predicted
D. Number of new defects injected when fixing existing defects
Explanation : Correct Answer is D. Error-feedback ratio is the number of new defects injected when fixing existing defects (e.g., 20 new defects generated in fixing 100 defects would be an error-feedback ratio of 20%).

Question: How do you best describe the primary role of an Agile leader?

Options:
A. Manage WBS, schedule and cost of project
B. Manage stakeholders
C. Manage work allocation to team members
D. Manage teams without managing their tasks
Explanation : Correct Answer is D. Agile leaders do not have to manage the tasks of the team members.
Your Answer :  No option selected.
Question: Assuming one-week iterations and a team of four developers, how many iterations will it take the team to complete a project with 27 story points if they have a velocity of 4?

Options:
A. 7
B. 4
C. 6
D. 24
Explanation : Correct Answer is A. Number of Iterations = 27/4 = 6.75 ~7
Your Answer :  No option selected.
Question: Name the XP technique where two people pair; one person who codes is the driver and the other person who thinks is the Navigator?

Options:
A. Pair Programming
B. Planning Poker
C. Planning Technique
D. Coding Technique
Explanation : Correct Answer is A. Pair Programming -- When you pair, one person codes—the driver. The other person is the navigator, whose job is to think.
Question: Decision Framing focuses majorly on,

Options:
A. Identifying types of decisions that need to be made
B. Stakeholders involved in the decision making process
C. Delegating decision making process
D. Manager taking the decision
Explanation : Correct Answer is B. Decision framing focuses on who gets involved in the decision process. Managers who make decisions without input from subordinates and peers make poor decisions. Engineers who make decisions without input from managers and peers make poor decisions. Who makes the decision is less important than getting the right people involved in the decision process.
Question: Which of the following is NOT true about the Iteration Demos?

Options:
A. It’s a concrete demonstration of the team’s progress
B. The demos help the team be honest about its progress.
C. Iteration demos are a closed affair and are shown only to a selected set of stakeholders
D. The demo is an opportunity to solicit regular feedback from the customers
Explanation : Correct Answer is C. Iteration demos are open to all stakeholders, and some companies even invite external customers to attend.
Question: Which of the following is a STORY?

Options:
A. "Full-screen demo option for job fair"
B. "Automate integration build"
C. "Deploy to staging server outside the firewall"
D. "Improve performance"
Explanation : Correct Answer is A. "Automate integration build" does not represent customer value, hence not a story. "Deploy to staging server outside the firewall" describes implementation details rather than an end result, and it doesn’t use customer terminology, hence not a story. "Improve performance" has no clear completion criteria, hence not a story.
Question: Which of the following factor will not assist in improving the project velocity?

Options:
A. Pay down Technical Debt
B. Offload Programmer duties
C. Reduce customer involvement
D. Provide needed resources
Explanation : Correct Answer is C. Customer Involvement should be improved to improve the project velocity.
Question: Which of the following BEST describes Horizontal Market Software?

Options:
A. Developed for many organizations
B. Developed and used across many industries
C. Developed for a dedicated customer
D. Developed for one organization
Explanation : Correct Answer is B. software that’s intended to be used across a wide range of industries. The rows of shrinkwrapped software boxes at your local electronics store are a good example of horizontal-market software. So are many web sites.
Question: At the second level of conflict, i.e. Disagreement, Team members distance themselves from one another to ensure they come out OK in the end or to establish a position for compromise they assume will come. They may talk offline with other team members to test strategies or seek advice and support. What becomes as important as solving the problem?

Options:
A. Self protection
B. Satisfy self ego
C. Aim to win
D. None of the above
Explanation : Correct Answer is A. At level 2, self-protection becomes as important as solving the problem. Team members distance themselves from one another to ensure they come out OK in the end or to establish a position for compromise they assume will come. They may talk offline with other team members to test strategies or seek advice and support.
Question: What financial return parameter will be BEST for comparing the values of two different cash flow streams?

Options:
A. Internal Rate of Return
B. Payback Period
C. Discounted Payback Period
D. Compound Interest
Explanation : Correct Answer is A. Internal Rate of Return (IRR) is used to express the return on project in % terms when comparing two different cash flow streams.
Your Answer :  No option selected.
Question: In a Fixed Price contract, the risk is beared by,

Options:
A. Supplier
B. Customer
C. Product Owner
D. Project Team
Explanation : Correct Answer is A. Obvious risk is on the side of the supplier. If the estimates are wrong, the project will lose money. Less obvious risks are the change request game, through which the supplier negotiates additional revenue through scope changes. If the supplier had badly underestimated the effort or risk, or quoted an unrealistically low price, the losses can even threaten the existence of the supplier, which also presents a problem to the customer.
Question: Self-organization implies a reliance on internal motivation of the team rather than external motivation. This is referred to as,

Options:
A. Delegatory management
B. Measurement based management
C. Democratic management
D. Autocratic management
Explanation : Correct Answer is A. Self-organization implies a reliance on internal motivation of the team rather than external motivation (i.e., a measurement target). Author Austin calls this delegatory management as contrasted with measurement-based management. He goes on to say, that "measurement-based management is in conflict with delegatory management. There is a negative interaction because of the implicit message of distrust that a measurement system conveys by the fact of its existence.
Question: A meeting where a team looks back on a past period of work so that they can learn from their experience and apply this learning to future projects is popularly known as?

Options:
A. Retrospective
B. Sprint Planning Meeting
C. Sprint Review Meeting
D. Status Meeting
Explanation : Correct Answer is A. Retrospective is the meeting where a team looks back on a past period of work so that they can learn from their experience and apply this learning to future projects.
Question: Who performs Value Point estimating?

Options:
A. Finance Team
B. Scrum Team
C. Product Team
D. Development Team
Explanation : Correct Answer is C. Value Point estimation is done by the Product Team.
Question: Who performs Value Point estimating?Options:A. Finance TeamB. Scrum TeamC. Product TeamD. Development Team Explanation : Correct Answer is C. Value Point estimation is done by the Product Team. Your Answer :  No option selected.
Question: Which of the following techniques would you use to detect problems within a process?

Options:
A. Sprints
B. Burn Up charts
C. Burn Down charts
D. Health checks
Explanation : Correct Answer is D. Health checks, often in the form of a questionnaire, lists required elements and qualities that jog our minds to help us remember the basic ingredients of agile. They help us determine how well the team is adhering to Agile methods.
Your Answer :  No option selected.
Question: Which of the following tests verify that units and combinations of units work together to perform the desired operations?

Options:
A. Unit tests
B. Component tests
C. Exploratory Tests
D. Usability tests
Explanation : Correct Answer is B. Component tests verify that units and combinations of units work together to perform the desired operations.
Your Answer :  No option selected.
Question: In absence of the Product Owner, who should assume the Product Owner's responsibilities at the Sprint planning meeting?

Options:
A. Scrum Master
B. Team
C. Person selected by the Product Owner
D. Person selected by the team
Explanation : Correct Answer is A. When the Product Owner is not present, the Scrum Master will take on the responsibility to prepare Product Backlog for the Sprint planning meeting.
Question: Which of the following is NOT included in the 'Story cards information'?

Options:
A. Estimated Value Points
B. Story description
C. Story dependencies
D. Velocity
Explanation : Correct Answer is D. Story cards information include Story name, Story description, Estimated work effort, Estimated value points, Requirements uncertainty, Story dependencies, Acceptance tests. Velocity is a measure of a team's rate of progress per iteration.
Your Answer :  No option selected.
Question: A Retrospective can be as short as 15 minutes or as long as 1 hour. The duration of the Retrospective can be dependent on all of the following EXCEPT :

Options:
A. Length of the Iteration
B. Level of conflict or controversy
C. Size of the team
D. Seniority of the Product Owner
Explanation : Correct Answer is D. Of all the listed options, the length of the Retrospective is not dependent on the seniority of the product owner. The length of the retrospective can be dependent on Length of Iteration, Level of conflict or controversy, size of the team and complexity (of technology, organization of the team, relationships with external department)
Question: Which of the following correctly defines 'Quantity of Function'?

Options:
A. Scope measured in terms of user stories, use cases, requirements, or features
B. Expressed as functionality produced for the time and effort
C. Expressed in terms of defect rate
D. Amount of effort expended in person-months
Explanation : Correct Answer is A. Quantity of function is, scope, measured in terms of user stories, use cases, requirements, or features (depending on a particular situation). In software, these may be measured ultimately as objects, modules, classes, or lines of code.
Your Answer :  No option selected.
Question: In a complete Product Planning structure, which of the following denotes the product planning structure with a medium range timeframe, story level of detail and capability commitment?

Options:
A. Release
B. Story
C. Roadmap
D. Wave
Explanation : Correct Answer is D. Wave is the Product Planning structure with Medium range time frame (3 months) with Story level capability and Capability commitment.
Your Answer :  No option selected.
Question: What are the four key terms by which the iterative part of Agile is defined?

Options:
A. timeboxed, releasable, agility and incremental
B. Iterative, feature-based, timeboxed, and incremental
C. Feature-based, timeboxed, agility and incremental
D. None of the above
Explanation : Correct Answer is B. Iterative development means that we build a partial version of a product and then expand that version through successive short time periods of development followed by reviews and adaptations. Feature-based delivery means that the engineering team builds features of the final product or, particularly with industrial products, at least a close representation of the final product (such as a simulation model). Iterations are constrained to produce a result within a certain period of time—a timebox (as short as 1–4 weeks for software). Timeboxes force closure; they force us to make something concrete, often before we are quite ready. Incremental development means that we build these products such that they could be deployed at the end of one or more of the iterations.
Question: Which of the following statements are NOT TRUE regarding Agility?

Options:
A. Agility is the ability to balance flexibility and stability
B. Agility is the ability to both create and respond to change in order to profit in a turbulent business environment
C. Agility is avoiding planning and lack of structure
D. Agility is ability to deliver customer value while dealing with inherent project unpredictability and dynamism
Explanation : Correct Answer is C. Agility is the ability to both create and respond to change in order to profit in a turbulent business environment. It is the ability to balance flexibility and stability.
Your Answer :  No option selected.
Question: There are different types of Retrospectives. These are Release Retrospectives, Project Retrospectives, Iteration Retrospectives and Surprise Retrospectives. What are Surprise Retrospectives?

Options:
A. Is conducted when an unexpected event changes your situation
B. Is conducted at the end of each Iteration
C. Is conducted half way of each project
D. Is suggested by the Scrum Master
Explanation : Correct Answer is A. Surprise Retrospective is conducted when an unexpected event changes your situation. It gives you a chance to reflect more deeply on your experiences and condense key lessons to share with the rest of the organization.
Your Answer :  No option selected.
Question: If your release is 12 iterations away, your velocity is 14 points, your risk exposure is one iteration and with a 10% chance, how many points will you have finished?

Options:
A. 154
B. 110
C. 86
D. 92
Explanation : Correct Answer is A. Using the following formula, risk_adjusted_points_remaining = (iterations_remaining - risk_exposure) * velocity / risk_multiplier --> points remaining = (12 - 1) * 14 = 154 points 10 percent chance: 154 / 1 = 154 points.
Your Answer :  No option selected.
Question: Which of the following reports visually shows the remaining estimated workload over the course of the project?

Options:
A. Product Backlog Burndown Report
B. Gantt Chart
C. Product Backlog
D. Sprint Chart
Explanation : Correct Answer is A. The Product Backlog Burndown report graphs remaining estimated workload over the course of the project. Workload at the start of each Sprint is measured by summing all open Product Backlog work estimates.
Your Answer :  No option selected.
Question: Every team needs to constantly evaluate and make appropriate adaptations in the following four areas:

Options:
A. Product value, Product quality, Team performance, Project status
B. Product value, Product quality, Team performance, Organization status
C. Product quality, Team performance, Project status, Project deliverables
D. Product value, Product Features, Team performance, Project status
Explanation : Correct Answer is A. Every team needs to constantly evaluate and make appropriate adaptations in the following four areas: Product value, Product quality, Team performance, Project status
Your Answer :  No option selected.
Question: What is the BEST tool for tracking the progress of the project and evaluating the ROI?

Options:
A. Sprint Backlog
B. Product Backlog
C. Iteration Backlog
D. None of the above
Explanation : Correct Answer is B.
Your Answer :  No option selected.
Question: Which of the following is NOT true about Kanban ?

Options:
A. A Kanban System visualises some unit of value, such as User Story, Minimal Marketable Feature or Plain Old Requirement
B. A Kanban System manages the flow of these units of value, through the use of Work In Process limits.
C. Kanban is same as a Task Board
D. It is a key tool in Lean Manufacturing
Explanation : Correct Answer is C. A Kanban System visualises some unit of value. This unit of value could be a User Story, Minimal Marketable Feature, Plain Old Requirement or something else. This is different from a task-board, which generally focuses on visualising the current tasks.
Your Answer :  No option selected.
Question: What is the relative contribution of feature X to the project if it has a value of 12 and the total value of all features is 35?

Options:
A. 0.38
B. 0.34
C. 2.91
D. 14.91
Explanation : Correct Answer is B. To calculate the relative contribution of each feature, divide its value by the sum of the Total Value of all features. Hence, relative contribution of feature X = 12/35 = 0.34.
Your Answer :  No option selected.
Question: What is the relative contribution of feature X to the project if it has a value of 12 and the total value of all features is 35?

Options:
A. 0.38
B. 0.34
C. 2.91
D. 14.91
Explanation : Correct Answer is B. To calculate the relative contribution of each feature, divide its value by the sum of the Total Value of all features. Hence, relative contribution of feature X = 12/35 = 0.34.
Your Answer :  No option selected.
Question: What is the process of defining and prioritizing the nonfunctional requirements for scaling known as?

Options:
A. Decomposition
B. Staging
C. Stanking
D. Prioritizing
Explanation : Correct Answer is B. The process of defining and prioritizing the nonfunctional requirements for scaling is called staging. Staging occurs prior to the start of the first Sprint and takes just one day. During this day, the nonfunctional scaling requirements for this particular project are determined and placed in the Product Backlog.
Your Answer :  No option selected.
Question: You have been assigned a New Project that is large, complex and uncertain. As a Project Manager, you will be using agile project management. Which of the following will you select while creating your team?

Options:
A. Team is expandable with the project
B. Large Team
C. Functional Manager is responsible for the team
D. None of the above
Explanation : Correct Answer is D. As per Agile methodology, it is best to work with small teams staffed by talented and experienced people and increase the number only when required.
Your Answer :  No option selected.
Question: Team A finished 43 story points in their last two-week iteration. Team B is working on a separate project and has twice as many developers. They also completed 43 story points in their last two-week iteration. What can you infer from this?

Options:
A. The story points of one team are not comparable to the story points of any other team.
B. Team A is twice as productive as Team B.
C. Team A should have more people on the team
D. Team B has the management support
Explanation : Correct Answer is A. The story points of one team are not comparable to the story points of any other team.
Your Answer :  No option selected.
Question: Who should participate in Iteration Planning?

Options:
A. Customer, Iteration Manager, Developers, Testers
B. Product Manager, Iteration Manager, Developers, Testers
C. Entire Project Team
D. Product Specialists, Customer, Iteration Manager, Developers, Testers
Explanation : Correct Answer is C. The entire project team—product manager, product specialists, customers, developers, testers, iteration manager, project leader—should participate in the iteration planning session as it provides everyone with the context for work to be accomplished during the iteration. Functional manager participation can help the team better understand strategic priority issues and demonstrates commitment to and support of the project.
Your Answer :  No option selected.
Question: Which of the following is NOT a Closed Story?

Options:
A. A recruiter can review resumes from applicants to one of her ads.
B. A recruiter can delete an application that is not a good match for a job.
C. A recruiter can manage the ads she has placed
D. A recruiter can change the expiration date of an ad
Explanation : Correct Answer is C. "A recruiter can manage the ads she has placed." This is not a closed story: Managing the ads she's placed is not something that is ever completely done. Instead, it is an ongoing activity.
Your Answer :  No option selected.
Question: Which of the following is NOT a Closed Story?

Options:
A. A recruiter can review resumes from applicants to one of her ads.
B. A recruiter can delete an application that is not a good match for a job.
C. A recruiter can manage the ads she has placed
D. A recruiter can change the expiration date of an ad
Explanation : Correct Answer is C. "A recruiter can manage the ads she has placed." This is not a closed story: Managing the ads she's placed is not something that is ever completely done. Instead, it is an ongoing activity.
Your Answer :  No option selected.
Question: A technique defined by Dean Leffingwell and Don Widrig for use cases is also used for Prioritization. This is a voting scheme where each stakeholder is given 100 points that he or she can use for voting in favour of the most important requirements. How they distribute the 100 points is up to them: 20 here, 10 there or even all 100 on a single requirement if that is their sole priority. This method is known as:

Options:
A. Monopoly Money
B. 100-Point method
C. Requirements Prioritization Money
D. Agile Prioritization
Explanation : Correct Answer is B. The 100-Point Method was originally developed by Dean Leffingwell and Don Widrig for use cases and is used for prioritization as well. It is a voting scheme where each stakeholder is given 100 points that he or she can use for voting in favour of the most important requirements. How they distribute the 100 points is up to them: 20 here, 10 there or even all 100 on a single requirement if that is their sole priority.
Your Answer :  No option selected.
Question: Which of the following is NOT done as part of Planning in Agile Project Management?

Options:
A. Risk Management
B. Product Vision
C. Slack
D. Done - Done
Explanation : Correct Answer is D. Done-Done is part of releasing.
Your Answer :  No option selected.
Question: Which of the following correctly defines the role of the Scrum Master?

Options:
A. Achieves initial and ongoing funding for the project by creating the project’s initial overall requirements
B. Is responsible for the Scrum process, for teaching Scrum to everyone involved in the project
C. Is responsible for developing the functionality
D. Is responsible for the Product Backlog
Explanation : Correct Answer is B. The ScrumMaster is responsible for the Scrum process, for teaching Scrum to everyone involved in the project, for implementing Scrum so that it fits within an organization’s culture and still delivers the expected benefits, and for ensuring that everyone follows Scrum rules and practices.
Your Answer :  No option selected.
Question: In XP, the code goes through four levels of completion. Which of the following states the right sequence?

Options:
A. Broken, Build, Ready for demo, Ready to release
B. Build, Ready for demo, Broken, Ready to release
C. Build, Ready for demo, Ready to release, Broken
D. Broken, Build, Ready to release, Ready for demo
Explanation : Correct Answer is A. your code goes through four levels of completion: 1. Broken. This only happens in your sandbox. 2. Builds and passes all tests. All versions in your repository are at least at this level. 3. Ready to demo to stakeholders. Any version marked with the “Iteration X" tag is ready for stakeholders to try. 4. Ready to release to real users and customers. Any version marked with the “Release Y" tag is production ready.
Your Answer :  No option selected.
Question: Which of the following is NOT a technique for estimating a story?

Options:
A. Expert Opinion
B. Analogy
C. Disaggregation
D. Decomposition
Explanation : Correct Answer is D. Decomposition is not a technique for estimating.
Your Answer :  No option selected.
Question: An informative workspace broadcasts information into the room. Of the following, which does NOT constitute to Informative workspace?

Options:
A. Big Visible Charts
B. Process Improvement Charts
C. Hand Drawn Charts
D. SRS Document
Explanation : Correct Answer is D. An informative workspace broadcasts information into the room. Examples are Big Visible Charts, Process Improvement Charts, Hand Drawn Charts and others
Your Answer :  No option selected.
Question: When a group of people come together as a team, they go through a specific sequence of group dynamics. Which of the following depicts the correct sequence?

Options:
A. Forming, Norming, Performing, Storming
B. Forming, Storming, Norming, Performing
C. Forming, Performing, Storming, Norming
D. Storming, Norming, Performing, Forming
Explanation : Correct Answer is B.
Your Answer :  No option selected.
Question: Forecasting the Financial value of a theme is the responsibility of,

Options:
A. Analysts
B. Product Owner
C. Project Manager
D. All Team Members
Explanation : Correct Answer is D. Forecasting the financial value of a theme is the responsibility of the product owner but it is a responsibility shared with all other team members—programmers, testers, analysts, project managers, and so on.
Your Answer :  No option selected.
Question: Which of the following is NOT true regarding Scope in Agile Projects?

Options:
A. Scope management in agile is primarily a function of "rolling wave" planning and the management of the product backlog.
B. "Scope creep" doesn't exist in agile projects, because scope is expected to change
C. Scope is controlled through the use of the backlog, rolling wave planning, and the protection of the iteration.
D. Scope is verified by the Product manager, who is responsible for accepting or rejecting the features completed each iteration.
Explanation : Correct Answer is D. Scope is verified by the customer, who is responsible for accepting or rejecting the features completed each iteration.
Your Answer :  No option selected.
Question: When should be the BEST time for the team to estimate a task?

Options:
A. Throughout the Iteration
B. During Iteration Planning
C. Task estimates are decided by the Scrum Master
D. At the time of Iteration Planning as well as during the iteration
Explanation : Correct Answer is D. Project Team will estimate a task at the time of Iteration Planning as well as during the iteration planning.
Your Answer :  No option selected.
Question: A long term plan of action designed to achieve a particular goal is referred to as,

Options:
A. Tactical Planning
B. Strategic Planning
C. Goal Planning
D. Roadmap Planning
Explanation : Correct Answer is B. strategy is a long-term plan of action designed to achieve a particular goal. A tactic is a method employed to achieve a certain goal. The goal pursued by strategic planning is at a higher level of abstraction than the goals pursued by tactics.
Your Answer :  No option selected
Question: The Levels of Listening by Whitworth states 3 Levels of listening. What does the third level, viz. Global listening refer to?

Options:
A. A hardwired connection is established between the coach and the speaker
B. The coach uses everything in the environment. Viz. speaker's tone of voice, posture, etc when listening at this level
C. The coach hears the speaker's words attentively
D. The coach only hears the global sounds and not the speaker's words
Explanation : Correct Answer is B. The coach uses everything in the environment when listening at Level III. The speaker’s tone of voice, posture, changes in room temperature, what noises are happening around them—all of these things are noticed and used by the coach.
Your Answer :  No option selected.
Question: Which of the following are MOST helpful in implementing collective code ownership in a team?

Options:
A. Version control
B. Pair programming
C. Continuous integration
D. Probability distribution
Explanation : Correct Answer is B.
Your Answer :  No option selected.
Question: The primary task in release planning is assigning stories to iterations, chiefly on the basis of _______________________

Options:
A. Value and Risk
B. Risk and Priority
C. Customer Requirements
D. Team ability and Value
Explanation : Correct Answer is A. The primary task in release planning is assigning stories to iterations, chiefly on the basis of value and risk.
Your Answer :  No option selected.
Question: What is Stress Testing?

Options:
A. Ensures that all of the components of the user interface behave as expected
B. Is done to ensure an application that can be easily used
C. Is done to gauge how well the application will perform under various workloads
D. Where the application is subjected to extreme values of users, transactions, or anything else that may put the application under stress
Explanation : Correct Answer is D. Stress Testing is where the application is subjected to extreme values of users, transactions, or anything else that may put the application under stress.
Your Answer :  No option selected.
Question: For projects of similar size and type, projects that that have a cumulative defect removal rate at the nodal point, have the shortest schedules, have the lowest quantity of effort in terms of person-months, and have the highest levels of user satisfaction after release. What is this nodal point?

Options:
A. 15%
B. 95%
C. 35%
D. 50%
Explanation : Correct Answer is B. Capers Jones' widely heralded book on software measurement concluded that "a cumulative defect removal rate of 95% on a project appears to be a nodal point where several other benefits accrue". For projects of similar size and type, these projects have the shortest schedules, have the lowest quantity of effort in terms of person-months, and have the highest levels of user satisfaction after release.
Your Answer :  No option selected.
Question: During which project management phase are the product stories delivered?

Options:
A. Envision
B. Speculate
C. Explore
D. Adapt
Explanation : Correct Answer is B. During the Speculate phase, the product stories are delivered. This phase involves planning and delivering tested stories in a short iteration, constantly seeking to reduce the risk and uncertainty of the project.
Your Answer :  No option selected.
Question: What is the outcome of a Sprint Planning Meeting?

Options:
A. Sprint Backlog
B. Product Backlog
C. Iteration Backlog
D. None of the above
Explanation : Correct Answer is A. The outcome of Sprint Planning meeting is the Sprint Backlog.
Your Answer :  No option selected.
Question: Which of the following correctly defines the Complex Story?

Options:
A. A User Story that comprises of multiple shorter stories
B. A User Story that that users can mark as inactive
C. User story that is inherently large and cannot easily be disaggregated into a set of constituent stories.
D. It is not a Story
Explanation : Correct Answer is C. Epics typically fall into two categories - Compound Stories and Complex Stories. the complex story is a user story that is inherently large and cannot easily be disaggregated into a set of constituent stories.
Your Answer :  No option selected.
Question: In the design-the-box activity, the entire team, including product team members customers, breaks into groups of four to six people. Their task is to design the product box—front and back. Which of the following is NOT Included ?

Options:
A. Graphic
B. Feature Description
C. Operating Requirements
D. Competitor's product name and features
Explanation : Correct Answer is D. In the design-the-box activity, the entire team, including product team members customers, breaks into groups of four to six people. Their task is to design the product box—front and back. This involves coming up with a product name, a graphic, three to four key bullet points on the front to "sell" the product, a detailed feature description on the back, and operating requirements.
Your Answer :  No option selected.
Question: You are part of the team that developed software for the organization's own use in serving the hospital customers. At one point, the CEO realizes that with some enhancements the software could be used to provide the same services to health insurers. The team is asked to make the changes and is able to bring an entirely new source of revenue into the company because of what the new software enabled. Under what revenue stream is this feature classified?

Options:
A. New Revenue
B. Incremental Revenue
C. Retained Revenue
D. Operational Efficiencies
Explanation : Correct Answer is A. New Revenue is the return on the project due to a new opportunity.
Your Answer :  No option selected
Question: Which of the following explains 'Retained Revenue'?

Options:
A. revenue due to a new opportunity
B. additional, incremental revenue from existing customers
C. revenue an organization will lose if the project is not performed.
D. Option A and C
Explanation : Correct Answer is C. Retained revenue refers to the revenue an organization will lose if the project is not performed.
Your Answer :  No option selected.
Question: Which of the following explains 'Retained Revenue'?

Options:
A. revenue due to a new opportunity
B. additional, incremental revenue from existing customers
C. revenue an organization will lose if the project is not performed.
D. Option A and C
Explanation : Correct Answer is C. Retained revenue refers to the revenue an organization will lose if the project is not performed.
Your Answer :  No option selected.
Question: What are the planning horizons in the planning onion that the agile teams are majorly involved in an Agile project?

Options:
A. Strategy, Portfolio, Product
B. Product, Release, Iteration
C. Release, Iteration, Day
D. Product, Iteration, Day
Explanation : Correct Answer is C. Most agile teams are only concerned with the three innermost levels of the planning onion, i.e. Release, Iteration and Day.
Your Answer :  No option selected.
Question: Which of the following does NOT explain Refactoring?

Options:
A. It is the process of changing the structure of code—rephrasing it— without changing its meaning or behaviour.
B. It is used to improve code quality
C. It eases adding new features
D. It reduces bugs drastically
Explanation : Correct Answer is D. Refactoring is the process of changing the structure of code—rephrasing it— without changing its meaning or behaviour. It’s used to improve code quality, to fight off software’s unavoidable entropy, and to ease adding new features.
Your Answer :  No option selected.
Question: In a project, all of the user stories are estimated and the sum of those estimates is 100 story points. Based on past experience, it is known that the team’s velocity is 9 story points per two-week iteration. How many iterations does the project need to complete the user stories?

Options:
A. 9
B. 11
C. 1
D. 90
Explanation : Correct Answer is B. Iterations = 100/9 = 11.1
Your Answer :  No option selected.
Question: Which report should NOT be shared with your stakeholders?

Options:
A. Defect reports
B. Status reports
C. Throughput reports
D. SLOC reports
Explanation : Correct Answer is D. Source Lines of Code (SLOC) reports should not be shared with the stakeholders, as they are flawed productivity metrics.
Your Answer :  No option selected.
Question: Intermediate points, usually from one month to three months apart that have both a project management and a technical function are known as,

Options:
A. Iteration burndown chart
B. Release
C. Wave
D. Roadmap
Explanation : Correct Answer is C. Waves, or milestones, are intermediate points, usually from one month to three months apart. Waves can have both a project management and a technical function. From a project management perspective, they provide a chance to review progress and make adjustments.
Your Answer :  No option selected.
Question: Activities are timeboxed processes that help the team move through the phases of the retrospective. Activities provide structure to help your team think together and have several advantages over freewheeling discussion. Activities don’t have to be elaborate or involved to be effective. Which of the following are NOT examples of activities that are useful in retrospectives ?

Options:
A. Brainstorming
B. Voting with Dots
C. Pair Interviews
D. Synergy
Explanation : Correct Answer is D. Activities don’t have to be elaborate or involved to be effective. Examples of activities that are useful in retrospectives include Brainstorming, Voting with Dots, doing Check-Ins, and performing Pair Interviews.
Your Answer :  No option selected.
Question: A verbal notice from one person to another, or to multiple people, that a milestone was reached is popularly known as,

Options:
A. Declaration Milestone
B. Publication
C. Announcement
D. Circular
Explanation : Correct Answer is A. The declaration milestone is a verbal notice from one person to another, or to multiple people, that a milestone was reached.
Your Answer :  No option selected.
Question: Which of the following charts shows the number of tasks completed each day of the iteration to monitor the progress?

Options:
A. Progression charts
B. Task Burndown chart
C. Task check off charts
D. Task charts
Explanation : Correct Answer is B. Many agile practitioners use a task burndown chart, which shows the number of tasks completed each day of the iteration to monitor progress.
Your Answer :  No option selected.
Question: A project with version control uses the version control system to mediate changes. It’s an orderly process in which developers get the latest code from the server, do their work, run all the tests to confirm their code works, then check in their changes. This process occurs several times a day for each pair. What is this process known as?

Options:
A. Version Control Management
B. Continuous Integration
C. Simple Integration
D. None of the above
Explanation : Correct Answer is B.
Your Answer :  No option selected.
Question: A stand-up meeting is conducted at a pre-set time every day where the whole team stands in a circle. One at a time, each person briefly describes new information that the team should know. At the Daily Scrum, what is NOT discussed?

Options:
A. What did I do yesterday?
B. What are my tasks for the coming week?
C. What will I do today?
D. What problems are preventing me from making progress?
Explanation : Correct Answer is B. In the Daily Scrum, participants specifically answer three questions: 1. What did I do yesterday? 2. What will I do today? 3. What problems are preventing me from making progress?
Your Answer :  No option selected.
Question: Which one of the following phases of project management includes developing a capability and/or feature based release plan to deliver the vision?

Options:
A. Envision
B. Speculate
C. Explore
D. Adapt
Explanation : Correct Answer is B. Speculate phase includes developing a capability and/or feature based release plan to deliver the vision.
Your Answer :  No option selected.
Question: A set of related user stories that may be combined together and treated as a single entity for either estimating or release planning is referred to as,

Options:
A. Theme
B. Epic
C. Story
D. Combined Story
Explanation : Correct Answer is A. Theme is a set of related user stories that may be combined together and treated as a single entity for either estimating or release planning.
Your Answer :  No option selected.
Question: Teams utilizing unfamiliar technology may need time for training prior to a project's launch and time to establish a development environment. This training may be included :

Options:
A. In Iteration 0
B. As a new story
C. Is out of project scope
D. None of the above
Explanation : Correct Answer is A. Iteration 0 helps teams balance anticipation with adaptation. Recognizing that iteration 0 doesn't deliver customer value pressures the team to keep it short.
Your Answer :  No option selected.

288 comments:

  1. Would help if questions were numbered, then one could provide feedback as to where the same question repeats itself, where the answer is a bit "flawed" or simply spelling mistakes or formatting issues. Globally, the process was OK, would have appreciated have the answers available on a separate page so that one could answer the questions and then view the answers. Many thanks though, was a great help

    ReplyDelete
  2. Passed in my second attempt and lucky to find 360pmo braindumps. Wish you all good luck in attempting ACP

    http://www.360pmo.com/home/products/pmi-acp-full-length-practice-exam/

    ReplyDelete
    Replies
    1. Mike: im also preparing acp exam.. can u plz suggest me which mock exam i ll prefer..

      Delete
  3. I got 79% in above 120 question and planning to give exam now.. Many question were NEW to me.

    But still i feel confident for exam..

    ReplyDelete
  4. Good set of questions. Useful for PMI-ACP definitely. Suggest the following:
    1. Avoid duplicate questions (a few are duplicates)
    2. The formatting has gone heywire inbetween
    3. Suggest to hide the answers and show upon click for each question as otherwise we invariably see some answers when scrolling down.

    Appreciate the great effort! Could also include a paid version

    ReplyDelete
  5. That helped... Thanks a lot!!!

    ReplyDelete
  6. This is really an incredible resource! Thank you for taking the time and sharing. You can also check out this PMI-ACP Study Guide for some positive reinforcement. Good luck!

    ReplyDelete
  7. Passed the PMI-ACP exam, with some help from these questions. It is a good additional resource for the test.

    ReplyDelete


  8. Thank you for the info. It sounds pretty user friendly. I guess I’ll pick one up for fun. thank u.

    Function Point Estimation Training

    ReplyDelete
  9. Hi friend iam providing the safe agile certification of various Courses online training.

    ReplyDelete
  10. Hi friend iam providing the safe agile training of various online training.

    ReplyDelete
  11. Hi friend iam providing the safe agile certification of various online trainings like PMP,PRINCE2,ACP,PSM,CSM.

    ReplyDelete
  12. Hi friend iam providing the safe agile certification of various online trainings like PMP,PRINCE2,ACP,PSM,CSM.

    ReplyDelete
  13. Hi friend iam providing thesafe agile certification training of various certification training.

    ReplyDelete
  14. Nice, Thanks for sharing .Also you check the best Prince2 Training Mumbai

    ReplyDelete
  15. Formally Known As Ulearnsystemssafe agile training in hyderbaf of various certification trainings,Low fee,2 days classroom training.

    ReplyDelete
  16. For latest and updated PMI-ACP certification dumps in PDF format contact us at completeexamcollection@gmail.com. Refer our blog for more details http://completeexamcollection.blogspot.in/

    ReplyDelete
  17. Nice blog, thanks for giving such information. Also you can check the best Agile Project Management Course

    ReplyDelete
  18. Good Info,
    Study of PMI PMI-ACP exam is not easy without having dumps. You can get PMI-ACP dumps from Dumps4Donwlaod.com this is the finest source for exam study material. They can provide you latest and actual exam questions with verified answers.

    ReplyDelete
  19. Nice article Jan on how to prepare for Learn Acp Certification. I just want to add a few more points like taking mock tests pertaining to each knowledge area and full length mock tests also form key elements behind cracking the Acp Certification successfully. I've recently passed Learn Six Sigma Master Black Belt exam. I took Learn Acp Certification .The training helped me clearing the exam in first attempt without any hassles.
    Acp Certification Hyderabad

    ReplyDelete
  20. Abur: Thanks so much for sharing this test and answers with us.. It is a lot effort and time from you. Many you coud do a many test and charge for those.

    Again, thanks a lot

    Many questions I didn´t know the answer, this means that I need study more.

    ReplyDelete
  21. We have been giving amazing examination guide and readiness material to the majority of our clients for quite a while now. Our dedicated specialists are working enthusiastically to give excellent test guide and concentrate material for the clients who need to pass affirmation tests in a solitary endeavor.
    Certsmarket

    ReplyDelete
  22. Awesome,
    Thank you so much for sharing such an awesome blog...

    remote resource

    ReplyDelete
  23. Well article, interesting to read…
    Thanks for sharing the useful information
    android development certification

    ReplyDelete
  24. This comment has been removed by the author.

    ReplyDelete
  25. There are free 50 ACP Sample questions here http://www.prozenics.com/Acp-QAs.html

    ReplyDelete
  26. I had amazing experience at www.realexamcollection.com because the material that was provided to me was according to my requirement. I didn’t need to go to any other place for preparation and found all what I need at one place. Questions and answers have been presented in very concise form so I learnt every concept with little effort. All what I had to do was to focus on the provided material. After choosing this material for my preparation everything became easier for me. It was not easy to pass this exam without such help so I am thankful for this sincere help and support. PMI PMI-ACP Dumps PDF

    ReplyDelete
  27. Passing the AI-100 exam is no more difficult, with latest AI-100 dumps pdf anyone can easily pass the AI-100 exam on the first attempt! The best thing is 100% success rate & money back assurance.

    https://www.realdumpspdf.com/exam/pmi-acp-dumps-pdf/

    Note:- New Questions has been added to the AI-100 PDF.

    Get the complete AI-100 Question Answers PDF & Start prepartion:- AI-100 Dumps 2019

    Product Features:

    1) 100% Success Rate

    2) Money Back Assurance

    3) Up-to-date Questions

    4) Instant Download

    5) Free Updates for 3 months

    ReplyDelete
  28. I was confused about the selection of a suitable guide for the preparation of PMI Agile Certified Practitioner (PMI-ACP) Exam. I could not find any better than PMI-ACP Dumps. If I appear in any further IT exam I will definitely download material from Realexamdumps.com. I suggest to all of you to take PMI-ACP Dumps PDF.

    ReplyDelete
  29. I would admire the miraculous quality of information which was conferring to the exam of PMI Agile Certified Practitioner. PMI-ACP Dump is efficient and affective source of knowledge. I’ll continue using materials from Dumps4download and will be referring to others.

    ReplyDelete
  30. When I was told about PMI-ACP dumps, first I downloaded free demo questions from Real exam dumps that gave me an opportunity to look into the material. All the information was authentic and the pattern of PMI-ACP questions and answer.was fully valid. I thank for this guide and appreciate such services.

    ReplyDelete
  31. I was able to do rapid preparation with PMI-ACP questions and answers that saved my time and unnecessary efforts. I work through the course and secure grand position with high grades. I think Exam4Help deserves thanks for boosting the career of so many IT students. I am feeling great after passing my exam with PMI-ACP dumps.

    ReplyDelete
  32. Question: During which project management phase are the product stories delivered? : Correct Answer is Explorer

    ReplyDelete
  33. Really impressed! Everything is very open and very clear clarification of issues. It contains truly facts. Your website is very valuable. Thanks for sharing. Digital marketing in pune

    ReplyDelete
  34. I was downloaded Acams CAMS dumps PDF in panic because I was not prepared and the time for the commencement of exam was not much. I did this on the suggestion of a friend but I checked the quality through free demo questions too. I am thankful to Dumpspass4sure.com for allowing this quality check. I simply prepared all the questions and answers that were carefully selected by the experts and put in this material and passed my exam with good grades. I am very happy for the right selection of Acams CAMS dumps at the right time. I am so satisfied with these services that I will use the same learning platform if I go for any further IT exam.

    ReplyDelete
  35. Good one!!!!! Correct answer for: During which project management phase are the product stories delivered? - Explore (not Speculate). I found the questions and explanations very useful. Thank you team!!!

    ReplyDelete
  36. Although Cisco is not an easy task to pass but I am happy to ace it by the first attempt. I can’t stop myself from appreciating the work at Dumpspass4sure. Experts have done excellent job. Pass4sure Cisco Dumps have been presented so comprehensively that I got all the concepts by the first read. They have reduced candidates’ efforts by sharing their experience in this form of service. Congratulations to everyone who used Pass4sure Cisco Question and answers like me.

    ReplyDelete
  37. I think EXAM4LEAD.COM deserves compliments and appreciation for all the useful work. FREE PMI-ACP DUMPS has been formed out of the honest and sincere work by the experts. I never thought PMI-ACP exam as easy as I took it after preparing from this concise guide. All the syllabus topics were dealt carefully by being relevant. It was not hard to infer the main idea of each topic. Without any difficulty I successfully solved all the questions. It was only through PMI PMI-ACP DUMPS 2020 updated that I got my target score. Very pragmatic approach has been followed while writing this guide book. I am thankful to experts for all the efforts they made for the preparation of this material.

    Download Full Exam & Pass 100% Success Guaranteed:

    PMI-200
    PMI-Agile Certified Practitioner (PMI-ACP)

    PMI-ACP
    PMI Agile Certified Practitioner

    https://www.exam4lead.com/pmi-acp-certification.html

    ReplyDelete
  38. Passing the PMI Agile Certified Practitioner is step toward IT Certification. You must have to pass your pmi-acp exam, so we friendly advice you to learn pmi-acp dumps pdf by us. Realdumpspdf fulfill your pmi-acp exam study material requirments and make 100% authentic pmi-acp exam dumps with actual pmi-acp exam question. And also valid pmi-acp exam practice question to make your preparation effective.

    For More Details: https://www.realdumpspdf.com/exam/pmi-acp-dumps-pdf/

    You also found these hidden benefits:

    Instant Download
    Free 90 days updates
    100% Passing Guarantee
    Updated Study Material
    Actual Exam Question
    Easy to learn and understand

    ReplyDelete
  39. PMI-ACP has won the trust of so many students by providing the material that fits for everyone with any type of background knowledge. My suggestions are to use this material for any type of IT exam. I could not have passed this exam if I could not find
    PMI-ACP
    at the right time. I will say thanks to examforsure for fulfilling the guarantee

    ReplyDelete
  40. There was nothing puzzling in PMI-ACP questions and answers. After checking the quality from demo questions, I downloaded the actual PDF file at very cheap price. I cannot express my excitement in words after getting guaranteed success in PMI-ACP and all this happened only with PMI-ACP dumps.

    ReplyDelete
  41. If you are in search of authentic study guide then you should visit DUMPSSURE.COM where you can download PMI-ACP dumps. This has been perfectly designed by qualified experts who are working to make a difference in the knowledge and results of IT students. The experts have an understanding of how the exam are conducted and what are the merits that are used to test candidates. With the use of all their knowledge about the field they have covered full syllabus in the form of Real PMI-ACP questions and answers. Not only this, but they have also developed Online Practice Test that will help you improve your understanding by improving your knowledge. The more you practice the better and desired consequences you will have. PMI-ACP pdf dumps guide is stamped with money back guarantee that assures you of your success and in case of failure you money will be returned. Download demo questions right now for trial and go for your success.

    Actual Exam Dumps Questions Answers

    ReplyDelete
  42. Accurate and valid exam dumps for which are verified by our professionals. Download the lastest exam question answer for from Dumpsadviser.

    ReplyDelete
  43. DumpsFactory proved to be a great help for me and nothing hurt me while seeking help from the qualified experts. PMI ACP Dumps played a vital role in my preparation and I was guaranteed to pass my IT exam with this study material. My need for an authentic and valid study material was fulfilled with PMI ACP Dumps. My recommendation for recommendation for everyone is the same guide. We are providing 10% discount, If you are interested then visit our site.

    ReplyDelete
  44. Get expert PMP Exam Project Management Professional (New Version) Question & Answer Dumps PDF Online. We Provide latest IT Certification Exams PDF for preparation Study Guide Test Practice for Success in exams. This is an online education portal

    ReplyDelete
  45. I passed my PMI PMI-ACP earlier this morning. You know what? I just use PMI PMI-ACP dumps from ExamforSure site, no other books at all! It is really helpful if you do not get much time to prepare your PMI exam. You should have a try. It won't let you down. Why do you want to take roundabout ways if there is a shortcut? Trust me or not. Good luck to you all.

    https://www.examforsure.com/pmi/pmi-acp-exam-dumps.html

    ReplyDelete
  46. My hearty thanks are for DumpsSure.com and all the people working for it. I downloaded Real PMI ACP dumps pdf from here which gave me an astute understanding of my discipline with all the technical required knowledge. I was guaranteed to pass my IT exam with PMI ACP questions and answers by the first attempt so expectedly and confidently I passed it. DUMPSSURE

    ReplyDelete
  47. It was my dream to pass PMI PMI-ACP exam but I could never gather courage or get a suitable study material. Finally a friend suggested me to download PMI PMI-ACP dumps PDF from DumpsForSure. I am thankful to the experts who carved it very smartly which helped me realize my dream. I am very happy for my incredible success with PMI PMI-ACP dumps and I suggest the same for everyone.

    ReplyDelete
  48. This comment has been removed by the author.

    ReplyDelete
  49. Recently, i sat for the exam and managed to pass. I have detailed my experiences here

    ReplyDelete
  50. Get The Best Deal Of 2021 January 40% Discount On
    I could not have done so astute preparation without PMI-ACP dumps pdf questions material as it gave me the most authentic information in the most concise form. I downloaded PMI-ACP dumps easily from Passexam4sure and started my preparation without any delay.

    ReplyDelete
  51. This comment has been removed by the author.

    ReplyDelete
  52. I prepared for my IT exam from PMI-ACP dumps and I think there is no study material of it match. I didn’t see any material of this value and I am thankful to everyone who has been the part of its creation. PMI-ACP dumps material is the most reliable material.

    ReplyDelete
  53. I had an amazing experience with RealDumpsCollection which brought me great success in my IT exam. PMI-ACP dumps was really helpful for covering all the syllabus contents in very short period of time. It was because of the handy format of this material which saved me time for practice on online practice test. The experts were very cooperative and showed a good disposition so I will suggest PMI-ACP dumps for everyone.

    ReplyDelete
  54. Passed this exam an hour ago, no hands on experience with using PMI PMP exam from using the free trial to practice for the test.

    I used: https://www.dumpsfactory.com/pmi/pmp-dumps.html

    ReplyDelete
  55. Nice blog!! keep up the great work. You can also check this Similar site for PMP

    ReplyDelete
  56. Realdumpspedia.com provides the excellent PMI-ACP practice exam questions for the IPMI Agile Certified PractitionerI am preparing for. Additionally, I used their online dumps which was the best user experience. I actually appreciate their excellent service.

    https://www.dumpsowner.com/pmi/pmi-acp-exam-dumps.html

    ReplyDelete
  57. It is so nice blog. I was really satisfied by seeing this blog.
    workday training
    workday online training

    ReplyDelete
  58. Through this Digital Marketing Training Institute in Panchkula you will become an expert in modules such as SEO, Social Media Marketing, PPC, Analytics, Content, Mobile, and Email Marketing. Our Social Media Marketing and PPC courses in Panchkula have trained end number of students. Work on real-world projects, learn the latest tools, and attend masterclasses led by the Google and Facebook certified team.


    - Get hands-on training on live projects!
    - Upgrade your resume
    - Get prepared for your dream job.
    - 120+ hours of high-quality training.
    - 10+ live projects.
    - 25+ digital marketing tools and platforms.

    ReplyDelete
  59. I would not be able to pass my PMI Agile exam without a suitable study material like PMI-ACP. It is only because of this guide that I covered my syllabus within a short period of time. This worthy material makes the experts praiseworthy who designed this helping guide. If I go for any further certification in future my definite selection will be PMI-ACP.

    For More Info Visit: https://www.dumpspool.com/pmi/pmi-acp-dumps.html

    ReplyDelete
  60. Amazing post. Informative and knowledgeable content. Keep sharing more stuff like this. Thank you.
    AI Patasala Data Science Courses in Hyderabad

    ReplyDelete
  61. For a limited time, get any exam PDF file in $30. You get REAL PMI questions and REAL answers to all of the hottest certification exams.

    Achieve a 100% Pass Rate on over 4000 Exams, prepare and quickly pass the tough IT certification exams.
    Unlimited access to IT training Exams and Certifications in PDF format.
    Original Questions and Verified Answers for Certification Exams.
    Instant Access to all 4000+ of our practice PDF downloads.

    Get Fully 100% Updated Dumps Questions: http://www.dumpssolutions.com

    ReplyDelete
  62. This comment has been removed by the author.

    ReplyDelete
  63. Several questions emerged in my mind before buying their PMI PMI-ACP Dumps
    . All my questions were answered and I really appreciate their immediate support and strong customer support with experience. Keep up this good job.

    ReplyDelete
  64. This was really one of my favorite website. Please keep on posting. Digital Marketing Classes In Pune

    ReplyDelete
  65. This comment has been removed by the author.

    ReplyDelete
  66. This comment has been removed by the author.

    ReplyDelete
  67. Many thanks for sharing such kind of info. It is actually not easy to meet the difficulties to Pass your PMP Exam, but if you have valid study material like DumpsToday PMI Exam Dumps. No doubt will pending to be successful.
    Hence its only need to get an authentic study material to prepare any of your exam, than nobody can stop you to be successful in your field..
    For More Details:-
    https://dumpstoday.com/

    ReplyDelete
  68. My focus was only on PMI-ACP dumps while preparing for my final IT exam. I didn’t consult any other source because I was given handsome knowledge about each topic in this concise guide book. I memorized questions and answers in PMI-ACP Dumps 2022 and easily aced my certification.

    ReplyDelete
  69. Thanks for providing the valuable information's, this is ver much helpful for the students. Also refer Digital marketing courses in Delhi for details about Online Digital marketing courses.

    ReplyDelete
  70. This comment has been removed by the author.

    ReplyDelete
  71. Thanks for sharing this informational article.
    Check out-
    Digital Marketing Courses in Delhi

    ReplyDelete
  72. Thank you for sharing this informational post. Very helpful!
    If you are interested in learning digital marketing, here is a complete list of the best online digital marketing courses with certifications. In this article, you will learn about digital marketing and its different strategies, the need for doing digital marketing, the scope of digital marketing, career opportunities after doing online digital marketing, and many more.
    Visit-
    Online Digital Marketing Courses

    ReplyDelete
  73. Hey great, I really delighted to find this useful informative blog to prepare PMP, which is the most valuable professional skill to earn and to elevate carrier. Thanks for sharing to get the glimpse of the exam. If anyone wants to learn Digital Marketing, Please join the highly demanded and most sought skill by the professionals in all streams due to the remarkable growth predicted by international survey agencies. So join today. Find out more detail at
    Digital marketing courses in france

    ReplyDelete
  74. This comment has been removed by the author.

    ReplyDelete
  75. This is a very informational blog. to know about digital marketing courses please visit.